FIR10-00473
| FIR-Aging Inspection | 12/23/2010 | 12/23/2010 | 12/28/2010 2:50:44 PM | | PART |
|
|
Site work in progress
|
FIR10-00463
| FIR-Aging Inspection | 12/23/2010 | 12/23/2010 | 12/28/2010 2:48:59 PM | | DONE |
|
|
Work in progress
|
FIR10-00495
| INSP-Sprinkler Rough-in | 12/23/2010 | 12/23/2010 | 12/23/2010 3:16:16 PM | P | PART |
|
|
don Phone #: ###-####
|
BLD10-01739
| FIRE-Conference | 12/23/2010 | 12/23/2010 | 12/23/2010 3:14:16 PM | P | DONE |
|
|
Conversation with John Schafer regarding project related fire alarm work and FIR permit for modification to the existing system due to remodel.
|
FIR10-00624
| INSP-Sprinkler Rough-in | 12/23/2010 | 12/23/2010 | 12/23/2010 3:06:08 PM | P | PART |
|
|
Overhead work at the two restrooms appears satisfactory, however missing approved plans on site.
|
BLD10-02764
| FIRE-Conference | 12/23/2010 | 12/23/2010 | 12/23/2010 3:04:21 PM | P | DONE |
|
|
Regarding issued correction notice information.
|
BLD10-02093
| FIRE-Final Inspection | 12/22/2010 | 12/23/2010 | 12/23/2010 3:02:48 PM | A | PASS |
|
|
Fire life safety completed satisfactory, inspection passed.
|
FIR10-00568
| INSP-Final Inspection | 12/23/2010 | 12/23/2010 | 12/23/2010 3:02:05 PM | A | PASS |
|
|
Scope of fire sprinkler work approved for final.
|
BLD10-00044
| FIRE-Conference | 12/23/2010 | 12/23/2010 | 12/23/2010 3:01:24 PM | A | DONE |
|
|
Regarding project related FIR permit work.
|
FIR10-00512
| INSP-Sprinkler Rough-in | 12/23/2010 | 12/23/2010 | 12/23/2010 2:59:35 PM | A | PART |
|
|
Noted two heads at a second floor utility room to be changed to quick response type sprinklers.
|