ELE12-03014
| ELE-Aging Inspection | 12/23/2016 | 12/23/2016 | 12/23/2016 12:09:09 PM | | DONE |
|
|
contractor will schedule with resident then schedule inspection
|
ELE12-01916
| ELE-Aging Inspection | 12/23/2016 | 12/23/2016 | 12/23/2016 12:07:40 PM | | DONE |
|
|
waiting on contractor
|
ELE16-04105
| Conference | 12/22/2016 | 12/23/2016 | 12/23/2016 12:06:51 PM | P | PASS |
|
|
Thomas// please call ahead Phone #: ###-####...
discussed what doing...said doing same thing as other side of duplex...will schedule for rough in inspection and final...
|
ELE16-01296
| Final | 12/23/2016 | 12/23/2016 | 12/23/2016 11:17:37 AM | P | PASS |
|
|
Final 6 units. Final project. ;) Phone #: ###-#### Inspection requested via web by Kevin Burke...
job complete...ok to final permit
|
ELE16-02719
| Final | 12/23/2016 | 12/23/2016 | 12/23/2016 10:11:02 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson....
corrections made...ok to final
|
ELE16-03726
| Electrical Rough-In | 12/23/2016 | 12/23/2016 | 12/23/2016 9:12:17 AM | A | PASS |
|
|
Mike Clay. Bathroom rough in. Phone #: ###-#### Inspection requested via web by Sean DeLacy...
ok cover full
|
ELE16-02401
| Electrical Rough-In | 12/22/2016 | 12/23/2016 | 12/23/2016 8:50:02 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Christy Cheney...
rough ok to cover
|
ELE16-03815
| Electrical Rough-In | 12/23/2016 | 12/23/2016 | 12/23/2016 8:19:14 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Cevyn Recla....
rough ok to cover
|