FIR08-00848
| INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/26/2008 5:54:38 PM | A | NH |
|
|
bryan Phone #: ###-####
|
FIR08-00851
| INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/26/2008 5:52:28 PM | A | PASS |
|
|
See inspection comments per S. Arellano.
|
BLD08-02545
| FIRE-Final Inspection | 12/22/2008 | 12/24/2008 | 12/24/2008 4:19:04 PM | P | PASS |
|
|
See inspection completed per S. Arellano.
|
FIR08-00796
| INSP-Final Inspection | 12/24/2008 | 12/24/2008 | 12/24/2008 4:15:05 PM | P | PASS |
|
|
Fire sprinkler permit okay for final per T. Frost.
|
FIR08-00847
| INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 4:09:55 PM | P | DEFR |
|
|
kenny Phone #: ###-####
|
BLD07-02324
| FIRE-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 4:09:23 PM | A | PART |
|
|
Need shell permit requested for final inspection prior to TI, preliminary inspection passed, noted one obstructed fire sprinkler head at the main entry to be adjusted before final approval.
|
FIR08-00428
| INSP-Final Inspection | 12/24/2008 | 12/24/2008 | 12/24/2008 4:06:16 PM | P | PASS |
|
|
Fire alarm permit finaled.
|
FIR08-00428
| INSP-Alarm Testing | 12/23/2008 | 12/24/2008 | 12/24/2008 4:05:51 PM | A | PASS |
|
|
Corrections verified for completion, fire alarm testing passed.
|
FIR08-00077
| INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 4:02:32 PM | A | PASS |
|
|
UG fire supply line permit finaled.
|
FIR08-00115
| INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 4:01:50 PM | A | PASS |
|
|
Fire sprinkler final inspection passed, see activity notes under attatched project UG permit FIR08-00077 for logged inspection activities related to this overhead permit. NOTE: contractor to provide backflow certification for the DCVA as discussed prior to next TI final.
|
FIR08-00791
| INSP-Sprinkler Rough-in/Hydro | 12/23/2008 | 12/24/2008 | 12/24/2008 3:56:04 PM | A | PART |
|
|
Fire sprinkler piping at both the womens and mens restrooms only are approved for cover at this time.
|
BLD08-02445
| FIRE-Conference | 12/23/2008 | 12/24/2008 | 12/24/2008 3:54:27 PM | A | DONE |
|
|
On site conference regarding project completion details.
|
FIR08-00299
| INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 3:53:18 PM | A | PART |
|
|
Functionality testing of the new and existing preaction risers completed today, PIV tamper at the west side needs adjustment, outside bell is not operational at the east side risers.
|
FIR08-00341
| INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 3:50:43 PM | A | PART |
|
|
Alarm and supervisory conditions for both the new sprinkler risers and the two existing risers tested today, functionality testing passed for all four preaction systems, noted the wall mounted PIV for the new west riser is not adjusted correctly to activate within 1/5 of valve closure, also discovered the outside bell at the existing riser is not operational. Discussed SD locations at beam pockets in the corridor and mounting heights of existing pull stations at the east side of the building.
|