Inspections for the day of: Wednesday, December 24, 2008.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00848 INSP-Final Inspection12/23/200812/24/200812/26/2008 5:54:38 PMANH
bryan Phone #: ###-####
FIR08-00851 INSP-Final Inspection12/23/200812/24/200812/26/2008 5:52:28 PMAPASS
See inspection comments per S. Arellano.
BLD08-02545 FIRE-Final Inspection12/22/200812/24/200812/24/2008 4:19:04 PMPPASS
See inspection completed per S. Arellano.
FIR08-00796 INSP-Final Inspection12/24/200812/24/200812/24/2008 4:15:05 PMPPASS
Fire sprinkler permit okay for final per T. Frost.
FIR08-00847 INSP-Final Inspection12/23/200812/24/200812/24/2008 4:09:55 PMPDEFR
kenny Phone #: ###-####
BLD07-02324 FIRE-Final Inspection12/23/200812/24/200812/24/2008 4:09:23 PMAPART
Need shell permit requested for final inspection prior to TI, preliminary inspection passed, noted one obstructed fire sprinkler head at the main entry to be adjusted before final approval.
FIR08-00428 INSP-Final Inspection12/24/200812/24/200812/24/2008 4:06:16 PMPPASS
Fire alarm permit finaled.
FIR08-00428 INSP-Alarm Testing12/23/200812/24/200812/24/2008 4:05:51 PMAPASS
Corrections verified for completion, fire alarm testing passed.
FIR08-00077 INSP-Final Inspection12/23/200812/24/200812/24/2008 4:02:32 PMAPASS
UG fire supply line permit finaled.
FIR08-00115 INSP-Final Inspection12/23/200812/24/200812/24/2008 4:01:50 PMAPASS
Fire sprinkler final inspection passed, see activity notes under attatched project UG permit FIR08-00077 for logged inspection activities related to this overhead permit. NOTE: contractor to provide backflow certification for the DCVA as discussed prior to next TI final.
FIR08-00791 INSP-Sprinkler Rough-in/Hydro12/23/200812/24/200812/24/2008 3:56:04 PMAPART
Fire sprinkler piping at both the womens and mens restrooms only are approved for cover at this time.
BLD08-02445 FIRE-Conference12/23/200812/24/200812/24/2008 3:54:27 PMADONE
On site conference regarding project completion details.
FIR08-00299 INSP-Final Inspection12/23/200812/24/200812/24/2008 3:53:18 PMAPART
Functionality testing of the new and existing preaction risers completed today, PIV tamper at the west side needs adjustment, outside bell is not operational at the east side risers.
FIR08-00341 INSP-Final Inspection12/23/200812/24/200812/24/2008 3:50:43 PMAPART
Alarm and supervisory conditions for both the new sprinkler risers and the two existing risers tested today, functionality testing passed for all four preaction systems, noted the wall mounted PIV for the new west riser is not adjusted correctly to activate within 1/5 of valve closure, also discovered the outside bell at the existing riser is not operational. Discussed SD locations at beam pockets in the corridor and mounting heights of existing pull stations at the east side of the building.