Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-03406 BLD-Final12/23/201412/24/201412/24/2014 2:48:32 PMPNR
Brad Phone #: ###-#### needs fire finals
BLD12-02886 BLD-Ceiling Grid Inspection12/24/201412/24/201412/24/2014 2:47:54 PMPPASS
Kent Phone #: ###-#### 3rd and 4th fl corr
BLD14-02793 BLD-Footing12/23/201412/24/201412/24/2014 12:17:52 PMAPEND
Phone #: 2086971241 >> Inspection requested via mobile web by Heron crew needs to spin footing 90 degs it needs to be a side loader
BLD14-02003 BLD-Foundation12/23/201412/24/201412/24/2014 12:15:19 PMAPEND
Partial Masonary wall grout/rebar,MTI scheduled to be onside 11am grout Phone #: ###-#### Inspection requested via web by Murph Naughtin
GCB14-00152 GCB-Fndatn/slab ins/fld vent12/23/201412/24/201412/24/2014 12:14:50 PMAPASS
Block and Tie for manufacutred home Randy ###-####
GCB14-00067 GCB-Final12/23/201412/24/201412/24/2014 9:39:29 AMAPASS
Vu ###-#### - call ahead
BLD14-01868 BLD-Conference12/23/201412/24/201412/24/2014 9:15:51 AMAPASS
Look at framing and Sheetrock inside of hood duct shaft. Phone #: ###-#### Inspection requested via web by Chris Eby
BLD14-01868 BLD-Ceiling Grid Inspection12/23/201412/24/201412/24/2014 9:15:27 AMAPASS
Phone #: ###-#### Inspection requested via web by Chris Eby
BLD14-03058 BLD-Wall Bracing12/23/201412/24/201412/24/2014 8:47:54 AMAPASS
BLD14-03199 BLD-Energy code compliance12/24/201412/24/201412/24/2014 8:47:39 AMAPASS
BLD14-03199 BLD-Framing/Rough-in12/23/201412/24/201412/24/2014 8:47:24 AMAPASS