Inspections for the day of: Tuesday, December 24, 2019.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-03426 FIRE-Final Inspection12/23/201912/24/201912/24/2019 10:27:28 AMAFAIL
Fire sprinkler modifications are required for the scope of work, a seperate permit is required for any and all modifications to fire sprinkler system.

call for access when you get there // Blaine Phone #: ###-####
FIR19-00489 INSP-Sprinkler Rough-in12/23/201912/24/201912/24/2019 8:19:16 AMAPART
Partial rough to cover inspection for overhead fire sprinkler piping above hardlids complete, notated city approved drawings with red ink areas approved for cover.

Todd is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD19-04602 FIRE-Final Inspection12/24/201912/24/201912/24/2019 8:18:01 AMAPASS
Fire alarm inspection is complete, fire sprinkler inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.

FIR19-00910 INSP-Final Inspection12/20/201912/24/201912/24/2019 8:16:42 AMAPASS
Previously noted items have been corrected, final fire aalrm inspection for area of work complete.

Needs to be done at 7:00am Phone #: ###-#### Inspection requested via web by Sam Ball