BLD06-02899
| Extend Permit 180 days | 12/21/2007 | 12/21/2007 | | P | |
|
|
|
FIR07-00102
| INSP-Final Inspection | 12/27/2007 | 12/27/2007 | 12/28/2007 7:32:09 AM | P | PASS |
|
|
Fire supply line permit finaled, see project related FIR permit for some activities regarding this case.
|
FIR07-00885
| INSP-Sprinkler Rough-in | 12/26/2007 | 12/27/2007 | 12/28/2007 7:28:51 AM | P | FAIL |
|
|
See approved plans for heads marked at some locations as missing, overspaced, or in need of addition.
|
BLD06-03180
| FIRE-Final Inspection | 12/26/2007 | 12/27/2007 | 12/27/2007 2:37:41 PM | A | FAIL |
|
|
Need to repair EM lights at four locations including the exit discharges, provide signage at the door to the FACP room, one missing PFE provided while on site, need to final project related fire alarm permit and recieve copies of NFPA 72 record of completion.
|
BLD07-01877
| FIRE-Final Inspection | 12/26/2007 | 12/27/2007 | 12/27/2007 12:36:01 PM | A | PASS |
|
|
Noted items in need of repair are finished, fire life safety inspection passed.
|
BLD07-02356
| FIRE-Final Inspection | 12/26/2007 | 12/27/2007 | 12/27/2007 12:34:48 PM | A | FAIL |
|
|
Need the project related fire alarm and sprinkler permits finaled prior to BLD life safety approval, noted items from the previous visit including hardware at the east exit door are corrected, EM lights and exit signage tested okay, job is not in condition for life safety final at this time.
|
FIR07-00950
| INSP-Final Inspection | 12/26/2007 | 12/27/2007 | 12/27/2007 12:31:09 PM | A | PASS |
|
|
C/N items are completed and verified for functionality, inspection passed, permit finaled.
|
FIR07-00943
| INSP-Final Inspection | 12/26/2007 | 12/27/2007 | 12/27/2007 12:29:53 PM | A | FAIL |
|
|
Fire alarm initiation and notification devices functioned properly, however the overhead music system needs to shut down upon activation of the building fire alarm, remainder of testing passed.
|
FIR06-00540
| INSP-Sprinkler Rough-in/Hydro | 12/26/2007 | 12/27/2007 | 12/27/2007 12:26:05 PM | A | PART |
|
|
OH hydrostatic testing for the 3rd floor SW quad passed, OH rough-in inspection also completed and okayed for cover as noted, two minor items repaired while on site, one head as annotated on plans to be relocated due to shadowing at an adjacent wall-can be verified at next scheduled visit.
|
FIR07-00957
| INSP-Sprinkler Rough-in | 12/26/2007 | 12/27/2007 | 12/27/2007 12:22:00 PM | A | PART |
|
|
On site conference regarding head spacing at one spray booth to avoid cold soldering, no other items reviewed or inspected today.
|