BLD11-02887
| FIRE-Final Inspection | 12/27/2011 | 12/27/2011 | 12/27/2011 4:43:52 PM | P | PASS |
|
|
Fire life safety completed satisfactory.
|
BLD11-02950
| FIRE-Final Inspection | 12/27/2011 | 12/27/2011 | 12/27/2011 4:43:16 PM | P | PASS |
|
|
Fire life safety finaled. Inspection passed.
|
BLD11-03017
| FIRE-Final Inspection | 12/27/2011 | 12/27/2011 | 12/27/2011 4:42:33 PM | P | PASS |
|
|
Fire life safety inspection completed acceptable.
|
FIR11-00496
| INSP-Sprinkler Rough-in | 12/27/2011 | 12/27/2011 | 12/27/2011 3:12:20 PM | P | PART |
|
|
2nd floor north wing rough-in per dated plan annotations okayed as noted. Modifications to pipe routing, added heads at each unit bathroom to be reflected on revised drawings. Discussed possible light fixture obstructions, heads at two concealed spaces not yet installed, one missing hanger replaced while on site. Notified general contractor no sheetrock is to be installed prior to a rough-in approval.
|
BLD11-01039
| FIRE-Final Inspection | 12/27/2011 | 12/27/2011 | 12/27/2011 12:38:25 PM | P | PASS |
|
|
Fire life safety finaled.
|
FIR11-00414
| INSP-Final Inspection | 12/27/2011 | 12/27/2011 | 12/27/2011 12:38:00 PM | P | PASS |
|
|
Repair completed, final inspection and testing passed. Fire sprinkler permit finaled.
|
BLD11-02820
| FIRE-Final Inspection | 12/23/2011 | 12/27/2011 | 12/27/2011 12:36:50 PM | P | PASS |
|
|
Scope of work passed fire life safety inspection.
|