ESC05-00970
| BMP Violation | 12/27/2005 | 12/28/2005 | 12/28/2005 3:34:55 PM | A | PART |
|
|
Spoke with RP about addressing issues on c/n. He is waiting on gravel for delivery/parking pad. All other issues are being addressed. I will follow up.
|
ESC05-00971
| BMP Violation | 12/27/2005 | 12/28/2005 | 12/28/2005 3:34:46 PM | A | PART |
|
|
Spoke with RP about addressing issues on c/n. He is waiting on gravel for delivery/parking pad. All other issues are being addressed. I will follow up.
|
ESC05-01033
| BMP Violation | 12/27/2005 | 12/28/2005 | 12/28/2005 3:34:12 PM | A | PART |
|
|
Spoke with RP about addressing issues on c/n. He is waiting on gravel for delivery/parking pad. All other issues are being addressed. I will follow up.
|
ESC05-01297
| Complaint Inspection | 12/28/2005 | 12/28/2005 | 12/28/2005 1:31:26 PM | P | FAIL |
|
|
responded to complaint from ACHD, c/n issued to address the following: sediment barrier is needed along front of houses along Crescent Rim to prevent slope from washing into street, access control is need along properties on Ruby St., ESC signs need posted, mud must be removed from ROW, and trash manangement is needed. Must be completed by 12-29-05 or stop work may be issued. Contacted RP, will follow up.
|
ESC05-01391
| BMP Violation | 12/28/2005 | 12/28/2005 | 12/28/2005 1:31:14 PM | P | FAIL |
|
|
responded to complaint from ACHD, c/n issued to address the following: sediment barrier is needed along front of houses along Crescent Rim to prevent slope from washing into street, access control is need along properties on Ruby St., ESC signs need posted, mud must be removed from ROW, and trash manangement is needed. Must be completed by 12-29-05 or stop work may be issued. Contacted RP, will follow up.
|
ESC05-00675
| Conference | 12/28/2005 | 12/28/2005 | 12/28/2005 12:46:24 PM | P | PASS |
|
|
Spoke with RP about installation of water line. Job is on hold due to wet weather. RP will notify me when job is underway.
|
ESC05-00675
| Random Inspection | 12/28/2005 | 12/28/2005 | 12/28/2005 12:42:22 PM | P | CANC |
|
|
|
ESC05-01628
| BMP Violation | 12/28/2005 | 12/28/2005 | 12/28/2005 11:06:17 AM | P | PART |
|
|
Several issues on c/n have been addressed, however, ESC sign is not completed and secondary entrance gate is not padlocked. Contacted RP and left c/n will follow up.
|
ESC05-01628
| BMP Violation | 12/27/2005 | 12/28/2005 | 12/28/2005 11:05:19 AM | A | PART |
|
|
Areas needing work, access control at const. entrance off of Franklin. D. I. protection on Franklin by const. entrance. Workers parking area. Fill out lines on yellowstorm water sign.
|