FIR08-00754
| INSP-Sprinkler Rough-in/Hydro | 12/22/2009 | 12/28/2009 | 12/28/2009 4:51:02 PM | P | DEFR |
|
|
Intended for alarm final
|
FIR09-00622
| INSP-Final Inspection | 12/24/2009 | 12/28/2009 | 12/28/2009 4:28:50 PM | A | PART |
|
|
Completed testing for duct detectors at areas A , F and mezzanines, retest DD at area D tool crib and area B office passed, incorrect sample tube orientation at AHU 28 fixed while on site, manual pull stations throughout tested okay, tamper switches at the sprinkler riser okayed, need to verify correct test orfice sizes at riser manifold prior to flow switch testing, two duct detectors at the Jenny Craig production line lacking access due to floor finishes underway, verified missing a/v has been installed at area D warehouse, relay for mag locks at the main entry is not ready for testing per contractor.
|
BLD09-01427
| FIRE-Final Inspection | 12/24/2009 | 12/28/2009 | 12/28/2009 4:09:34 PM | A | PASS |
|
|
Fire life safety finaled.
|
BLD08-02600
| FIRE-Final Inspection | 12/28/2009 | 12/28/2009 | 12/28/2009 3:54:41 PM | A | PASS |
|
|
Fire life safety inspection passed, correction notice items completed.
|
FIR09-00364
| INSP-Final Inspection | 12/28/2009 | 12/28/2009 | 12/28/2009 3:53:40 PM | A | PASS |
|
|
Fire sprinkler permit work passed final inspection.
|