Inspections for the day of: Friday, December 28, 2012.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Sly
TitleBLD-COM/RES INSPECTOR
Phone #794-9465
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD12-01909 BLD-Other12/28/201212/28/201212/28/2012 2:12:47 PMPPASS
pat late as possible Phone #: ###-####
1st layer of rock and R C channel on Lid.......OK.
BLD12-02455 BLD-Wall Bracing12/27/201212/28/201212/28/2012 2:09:57 PMPPASS
eric Phone #: ###-####
BLD12-01896 BLD-Final12/27/201212/28/201212/28/2012 2:09:39 PMPNR
Charles Phone #: ###-####
Need electr permit and final.
BLD12-02890 BLD-Wall Bracing12/27/201212/28/201212/28/2012 11:32:02 AMAPASS
Matt Phone #: ###-####
ESC12-00750 Random Inspection12/27/201212/28/201212/28/2012 11:30:43 AMAPASS
Jamal phone
BLD12-01950 BLD-Footing12/27/201212/28/201212/28/2012 11:29:50 AMAPASS
Footing placement for new shearwall (20 yards)at 10:00AM.
MTI will be on site for visual inspection of six (6)embedded rebar with epoxy to tie in old footing, rebar placement for reinforcement, will collect cylinders for testing @ 10:00AM Phone #: ###-#### >> Inspection requested via web by Philip Allen
OK pending MTI inspection, tests and approvals.
ESC12-00737 Site Final12/27/201212/28/201212/28/2012 11:28:06 AMANR
Charles phone