Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-03381 BLD-Final12/27/201712/28/201712/29/2017 8:43:43 AMAPASS
Andrea Phone #: ###-####
BLD17-03533 BLD-Framing/Rough-in12/28/201712/28/201712/29/2017 6:49:02 AMPPEND
Kent Phone #: ###-#### ok after elec rough in
BLD17-01246 BLD-Final12/27/201712/28/201712/29/2017 6:47:58 AMPNR
Eric Phone #: ###-####
BLD17-00583 BLD-Other12/28/201712/28/201712/29/2017 6:47:47 AMPPASS
drop ceiling inspection on 3rd floor Phone #: ###-#### Inspection requested via web by David Banks
BLD17-03016 BLD-Footing12/27/201712/28/201712/29/2017 6:47:32 AMPPEND
Keith Phone #: ###-#### ok after spec inspection final signoff
BLD16-04337 BLD-Final12/27/201712/28/201712/28/2017 1:25:06 PMANR
Phone #: ###-#### Inspection requested via web by Jim Williams
BLD17-02224 BLD-Final12/27/201712/28/201712/28/2017 1:24:15 PMANR
Phone #: ###-#### Inspection requested via web by Jim Williams
BLD17-00583 BLD-Other12/27/201712/28/201712/28/2017 11:14:11 AMAPASS
5th floor pre rock inspection as well as 4th floor wall inspections and consult on 4 inch fire sprinkler pipe Phone #: ###-#### Inspection requested via web by David Banks
BLD17-04404 BLD-Framing/Rough-in12/27/201712/28/201712/28/2017 11:13:47 AMAPASS
Inspection of air infiltration work prior to Insulation Phone #: ###-#### Inspection requested via web by Ryan Allen