FIR09-00504
| FIR-Aging Inspection | 12/29/2009 | 12/29/2009 | 12/30/2009 11:48:02 AM | | DONE |
|
|
Work in progress, pending site inspection request.
|
FIR09-00286
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 5:04:02 PM | A | PART |
|
|
Correction notice items completed, final pending satisfactory alarm permit final for system supervision.
|
FIR09-00285
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 5:03:35 PM | A | PART |
|
|
Correction notice items completed, final pending satisfactory alarm permit final for system supervision.
|
FIR09-00284
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 5:03:08 PM | A | PART |
|
|
Correction notice items completed, final pending satisfactory alarm permit final for system supervision.
|
FIR09-00283
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 5:02:50 PM | A | PART |
|
|
Correction notice items completed, final pending satisfactory alarm permit final for system supervision.
|
FIR09-00282
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 5:02:29 PM | A | PART |
|
|
Correction notice items completed, final pending satisfactory alarm permit final for system supervision.
|
BLD09-00017
| FIRE-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 4:46:33 PM | A | FAIL |
|
|
Project related fire alarm permit has not passed inspection, noted closures at two main doors need adjusted.
|
FIR09-00305
| INSP-Final Inspection | 12/29/2009 | 12/29/2009 | 12/29/2009 4:44:56 PM | P | FAIL |
|
|
Lacking account set up at offsite monitoring.
|
FIR09-00304
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 4:44:00 PM | A | FAIL |
|
|
Signals could not be verified due to missing account information and set-up.
|
FIR09-00683
| INSP-Sprinkler Rough-in/Hydro | 12/28/2009 | 12/29/2009 | 12/29/2009 4:36:55 PM | P | PART |
|
|
Overhead fire sprinkler work is approved for cover at the drop ceilings throughout the tenant improvement area, two added uprights at the shell side okayed to maintain adequate coverage.
|
FIR09-00706
| INSP-Final Inspection | 12/29/2009 | 12/29/2009 | 12/29/2009 4:34:21 PM | P | FAIL |
|
|
See plan annotations and highlighted areas in need of revision including overspaced heads, one obstructed area, and two locations which exceed min. spacing.
|
FIR09-00654
| INSP-Sprinkler Rough-in | 12/29/2009 | 12/29/2009 | 12/29/2009 4:32:43 PM | P | PART |
|
|
Initialed plans at one room approved for drop ceiling cover at overhead fire sprinkler modifications, discussed project schedule with contractor.
|
FIR09-00736
| INSP-Sprinkler Rough-in | 12/29/2009 | 12/29/2009 | 12/29/2009 4:31:27 PM | P | PART |
|
|
Okay to cover heads at the new rated ceiling enclosure- see initialed plans on site.
|
FIR09-00701
| INSP-Final Inspection | 12/29/2009 | 12/29/2009 | 12/29/2009 4:29:06 PM | P | PASS |
|
|
Scope of fire sprinkler work completed satisfactory.
|
FIR09-00622
| INSP-Final Inspection | 12/24/2009 | 12/29/2009 | 12/29/2009 4:28:18 PM | A | PART |
|
|
Duct detectors at the new production area passed testing, mag lock at the main entry/exit needs repair, coordinated notification testing for 12/31 per discussion.
|
BLD08-01146
| FIRE-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 4:26:06 PM | A | FAIL |
|
|
Both project related fire alarm and sprinkler permits failed final inspection.
|
FIR09-00210
| INSP-Final Inspection | 12/29/2009 | 12/29/2009 | 12/29/2009 4:25:02 PM | P | FAIL |
|
|
Voice evacuation at unit 1201 did not function, smoke alarm at the NW bedroom is not interconnected-see review notes item #29.
|
FIR08-00446
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 4:23:01 PM | A | FAIL |
|
|
Heads at new 401 canopies have been installed via a series of 1/2" brass nipple extenders. See NFPA 13 2007 8.15.19.1.
|
FIR08-00754
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 4:13:02 PM | A | FAIL |
|
|
Missing notification appliances at four locations including the pump room, 1st level parking garage, attendant restroom, and basement level storage area. Notification appliances at the parking deck levels 2 through 8 passed functional testing, provide state certifications for the existing east and west elevators.
|
FIR09-00364
| INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 4:07:07 PM | A | PASS |
|
|
Fire sprinkler permit final approved.
|
FIR09-00304
| INSP-Final Inspection | 12/23/2009 | 12/29/2009 | 12/23/2009 1:21:26 PM | A | CANC |
|
|
Please call 30 min prior to inspection. If you have any questions, please call Mike at ###-####. Phone #: ###-#### Internet Inspection Request from: Shawna Gates Inspection cancelled from web by: Shawna Gates
|