PLM01-01874
| Water and/or Sewer | 12/6/2001 | 12/3/2001 | 12/6/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 330 On 12/6/2001 9:33:07 AM partial water service ok need to test tie in
|
PLM01-03985
| Final | 11/30/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | A | PASS |
|
|
###-#### CRAIG sewer and water test ok 12/3/2001 10:28:50 AM
|
PLM01-04046
| Plumbing Rough-in | 11/30/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | A | PASS |
|
|
###-####
|
PLM01-01937
| Final | 11/30/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | A | CANC |
|
|
###-#### MALCOM
|
PLM01-04032
| Sprinkler (Final) | 11/30/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | A | FAIL |
|
|
Scheduled by Inspector: 330 On 11/30/2001 3:12:13 PM needs 160 upstream of the pvb, tie in ok expose water line from tie in to water service to pvb, replace all 80 psi utility piping with 160 min. psi service piping from tie in to pvb, line must grade by gravity back to drain valve, have valve re-certified, call for re-inspection. 12/3/2001 10:44:05 AM
|
PLM01-04047
| Water and/or Sewer | 11/30/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 330 On 11/30/2001 3:15:08 PM check the test on the water service sewer to building is in and th 12/3/2001 8:45:58 AM e water service is to the meter location 12/3/2001 8:46:17 AM
|
PLM01-03984
| Plumbing Rough-in | 11/30/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | A | PART |
|
|
Scheduled by Inspector: 330 On 11/30/2001 3:34:45 PM 10 0r 11 turn on water and strap up tub valves, install waste arms 12/3/2001 11:02:27 AM
|
PLM01-03292
| Final | 11/30/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | A | FAIL |
|
|
###-#### JOHN turn on water and complete trim 12/3/2001 9:26:15 AM
|
PLM01-02442
| Plumbing Rough-in | 11/30/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 11/30/2001 at 16:28:19. Contact: ###-####.
|
PLM01-03292
| Final | 12/3/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 330 On 12/3/2001 10:20:52 AM
|
PLM01-03984
| Plumbing Rough-in | 12/3/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | P | PART |
|
|
Scheduled by Inspector: 330 On 12/3/2001 11:01:42 AM nort side of the east wing ok to cover 12/3/2001 4:28:34 PM
|
PLM01-04031
| Other | 12/3/2001 | 12/3/2001 | 12/3/2001 12:00:00 AM | P | PART |
|
|
Added by Inspector: 330 On 12/3/2001 1:39:16 PM conference, went over a couple of ways to plumb the ground work, side inlet looked like it would work ok, went over fittings, wyes/santees, etc., told him about bringing the existing sewer under the addition up to approved material, and all that kind of junk.
|