Inspections for the day of: Monday, December 30, 2013.
Number of inspections: 20
Percentage of inspections complete: 95 %
Percentage of inspections not complete: 5 %
Contact Information
InspectorJim Sly
TitleBLD-COM/RES INSPECTOR
Phone #794-9465
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-00886 General Inspection12/24/201312/24/2013   
BLD13-03556 BLD-Final12/30/201312/30/201312/30/2013 4:52:38 PMPPASS
DAVID Phone #: ###-####
OK for Perm Occ.
BLD13-02140 BLD-Wall Bracing12/30/201312/30/201312/30/2013 4:43:43 PMPPASS
JACK Phone #: ###-####
BLD13-02549 BLD-Framing/Rough-in12/30/201312/30/201312/30/2013 4:42:10 PMPPASS
rick Phone #: ###-####
GCB13-00131 GCB-Energy12/30/201312/30/201312/30/2013 4:37:47 PMPPASS
Braydon ###-####
GCB13-00129 GCB-Energy12/30/201312/30/201312/30/2013 4:34:22 PMPPASS
Braydon ###-####
BLD13-03280 BLD-Final12/27/201312/30/201312/30/2013 2:45:02 PMPCANC
zach Phone #: ###-####
Need fire final.......
BLD13-02737 BLD-Final12/30/201312/30/201312/30/2013 2:02:03 PMPPASS
I have been told that all other inspections have been passed. Thanks Phone #: ###-#### >> Inspection requested via web by Scott Stimpson
BLD13-02737 DOC - Permit Finaled12/30/201312/30/201312/30/2013 2:01:51 PMPPASS
BLD13-01246 BLD-Energy code compliance12/27/201312/30/201312/30/2013 1:59:34 PMAPASS
travis Phone #: ###-####
BLD13-01246 BLD-Framing/Rough-in12/27/201312/30/201312/30/2013 1:58:50 PMAPASS
travis Phone #: ###-####
BLD13-02968 BLD-Final12/30/201312/30/201312/30/2013 1:07:20 PMPFAIL
Preston Phone #: ###-####
See previous notes. Check for soffit vent covers.
BLD13-02968 BLD-Framing/Rough-in12/30/201312/30/201312/30/2013 1:05:48 PMPNR
Preston Phone #: ###-####
Need Engineering or something on plan.......See beam point load at S. end? Need Concrete strips to drive on in yard? Required? Approved plan shows Bldg. 15' from house. Need revised approved plan showing bldg. closer to house.
BLD13-02914 BLD-Final12/27/201312/30/201312/30/2013 12:26:14 PMAPASS
Ready for final now. Please call ###-#### before coming to make sure the home is open. Phone #: ###-#### >> Inspection requested via web by Olga Kondratyuk
BLD13-02914 DOC - Permit Finaled12/30/201312/30/201312/30/2013 12:26:03 PMPPASS
BLD13-02974 BLD-Conference12/29/201312/30/201312/30/2013 11:07:28 AMADONE
Looked at job....Framers are not putting any windows in on East Side.......One on 1st floor framed in......but sheated over with OSB.
BLD13-03350 BLD-Foundation12/26/201312/30/201312/30/2013 10:54:11 AMAPASS
Eric Phone #: ###-####
MIS13-00333 BLD-Conference12/23/201312/30/201312/30/2013 10:46:03 AMADONE
Checked back......No work since Correction notice.
BLD13-01287 BLD-Wall cover12/27/201312/30/201312/30/2013 10:33:48 AMAPART
More units ready for 2nd layer on ceiling
Some ready for taping

>> Inspection requested via web by Mike McHargue
Select units.....OK 1st layer......OK 2nd layer.
BLD13-02737 BLD-Conference12/30/201312/30/201312/30/2013 7:59:38 AMPCANC
I have been told that all inspections have been completed finally. Just need Building now. Let me know if this is right.
Thanks Phone #: ###-#### >> Inspection requested via web by Scott Stimpson Inspection cancelled from web by: Scott Stimpson