Inspections for the day of: Wednesday, December 31, 2014.
Number of inspections: 9
Percentage of inspections complete: 89 %
Percentage of inspections not complete: 11 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00344 INSP-Sprinkler Rough-in12/29/201412/30/2014 P 
Inspection for 1st floor soffits area a and b. Contact is Raul ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Carter II
FIR14-00470 INSP-Final Inspection12/30/201412/31/201412/31/2014 3:27:15 PMAPART
Need to adjust PIV tamper and flow switch at the system riser 1st floor. Remainder of inspection passed.
FIR14-00778 INSP-Sprinkler Rough-in12/30/201412/31/201412/31/2014 3:25:20 PMPDEFR
FIR14-00708 INSP-Sprinkler Rough-in12/30/201412/31/201412/31/2014 3:24:55 PMPDEFR
BLD14-03406 FIRE-Final Inspection12/30/201412/31/201412/31/2014 3:24:27 PMPNR
Need project related fire sprinkler permit work completed and scheduled for inspection prior to fire life safety final.
BLD13-03348 FIRE-Final Inspection12/30/201412/31/201412/31/2014 3:21:46 PMAPART
TCO approved pending trade related fire alarm permit work.
BLD13-03291 FIRE-Final Inspection12/30/201412/31/201412/31/2014 3:20:31 PMAPART
TCO approved pending trade related fire alarm final.
BLD13-00244 FIRE-Final Inspection12/30/201412/31/201412/31/2014 11:41:14 AMAPASS
Scope of permit work completed. Fire life safety inspection passed. Need to repost suite address numbers as discussed.
FIR14-00703 INSP-Final Inspection12/30/201412/31/201412/30/2014 3:32:33 PMAPASS
Verified C/N item. Final walkthrough completed (12/30). Fire sprinkler permit finaled.