Inspections for the day of: Thursday, December 5, 1996.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorWes Worcester
TitleBLD-COM/RES INSPECTOR
Phone #340-1490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD96-01155 INSP - Energy code compliance12/4/199612/5/199612/5/1996 12:00:00 AMAPASS
insulate t fitting in attic
BLD96-01988 INSP - Carpentry12/4/199612/5/199612/5/1996 12:00:00 AMANH
no one other than excavator there
BLD96-02224 INSP - Letter of compliance12/5/199612/5/199612/5/1996 12:00:00 AMAPASS
c/c issued
BLD96-02224 INSP - Final12/4/199612/5/199612/5/1996 12:00:00 AMAPASS
FINAL REINSPECT
BLD96-02274 INSP - Framing/Rough-in12/4/199612/5/199612/5/1996 12:00:00 AMAFAIL
punch list of 9 items on truss eng and tji installation...partial only as info is needed from tji and truss co before continuing
BLD96-02533 INSP - Framing/Rough-in12/3/199612/5/199612/5/1996 12:00:00 AMAPART
doing minor truss bracing
BLD96-02612 INSP - Framing/Rough-in12/4/199612/5/199612/5/1996 12:00:00 AMAPASS
FRAME REINSPECT
BLD96-02612 INSP - Energy code compliance12/5/199612/5/199612/5/1996 12:00:00 AMPPASS
BLD96-03001 INSP - Letter of compliance12/5/199612/5/199612/5/1996 12:00:00 AMPPASS
c/c #12331 issued
BLD96-03001 INSP - Final12/4/199612/5/199612/5/1996 12:00:00 AMPPASS
ROOF FINAL. PLEASE LEAVE C OF C LETTER IF FINAL OK.
BLD96-03045 INSP - Footings12/5/199612/5/199612/5/1996 12:00:00 AMPPART
CHECK THE HOLES..only one done. one pilot done, 2nd being done
BLD96-02394 INSP - Framing/Rough-in12/5/199612/5/199612/5/1996 12:00:00 AMPPASS
working on minor truss bracing
BLD96-01875 INSP - Conference12/5/199612/5/199612/5/1996 12:00:00 AMPPASS
discussed infiltration package and he is in process of doing on site
BLD96-01875 INSP - Energy code compliance12/5/199612/5/199612/5/1996 12:00:00 AMPPASS
in process of placing baffles and will finish insulating ...addn not necessarily governed by BCEC, however he is going to do
BLD96-01875 INSP - Framing/Rough-in12/5/199612/5/199612/5/1996 12:00:00 AMPPASS
1:30 & 2 PM