BLD11-02324
| FIRE-Sprinkler Rough-in | 12/5/2011 | 12/5/2011 | 12/5/2011 5:56:46 PM | P | PART |
|
|
Overhead fire sprinkler work as marked on approved plans to date are approved for cover.
|
BLD11-01556
| FIRE-Final Inspection | 12/2/2011 | 12/5/2011 | 12/5/2011 5:46:01 PM | A | DEFR |
|
|
No fire related signatures required on this project per permit details.
|
BLD11-01845
| FIRE-Sprinkler Rough-in | 12/5/2011 | 12/5/2011 | 12/5/2011 5:42:36 PM | A | PART |
|
|
OH work at two areas approved for cover. Ref. sprinkler plans for annotations.
|
FIR08-00604
| INSP-Alarm Testing | 12/2/2011 | 12/5/2011 | 12/5/2011 5:39:54 PM | A | PART |
|
|
Completed notification testing at building 1 garage, building 2 and 3 garages including 1st -4th floors and building 4 garage. Verified previous correction items and repairs at buildings 2 and 3, record drawings for field changes finished with the exception of the first floor levels. Noted items today include one non-functional av at the 2nd floor #3 corridor, insufficient dB at resident storage bldg. #3, dB levels at the finished model units are not adequate, DH at elevator lobbies building #2 did not release. Discussed schedule and items for next test date.
|
BLD11-02584
| FIRE-Final Inspection | 12/2/2011 | 12/5/2011 | 12/5/2011 12:20:28 PM | A | PASS |
|
|
Fire life safety inspection passed.
|