ESC12-00398
| Random Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 5:07:05 PM | P | FAIL |
|
|
Verbal to RP: protect the storm drain no the corner of 8th ST. and Main street. Will follow up on 12/6/2012 p.m.
|
ESC12-00676
| Aging Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 4:30:19 PM | | PASS |
|
|
Almost complete with final stabilization measures.
|
ESC12-00929
| General Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 3:58:48 PM | | PASS |
|
|
Will be inspecting the project with the RP to address any area that still need to be staabilized on 12/6/2012
|
ESC10-00657
| General Inspection | 12/4/2012 | 12/5/2012 | 12/5/2012 3:42:37 PM | P | NH |
|
|
Could not receive access into the property.
|
ESC12-00425
| Aging Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 1:54:57 PM | | DONE |
|
|
Permit finaled
|
ESC12-00425
| DOC - Permit Finaled | 12/5/2012 | 12/5/2012 | 12/5/2012 1:54:41 PM | P | PASS |
|
|
|
ESC11-00627
| General Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 1:54:24 PM | | DONE |
|
|
Vertical construction has begun on many of the lot but not all.
|
ESC12-00759
| Aging Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 1:53:24 PM | | PASS |
|
|
NO activity could not reach back yard
|
ESC12-00555
| Aging Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 1:52:44 PM | | PASS |
|
|
|
ESC12-00731
| Aging Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 1:52:21 PM | | PASS |
|
|
|