ELE00-03086
| ELE-Aging Inspection | 12/5/2013 | 12/5/2013 | 12/13/2013 3:57:34 PM | | DONE |
|
|
Homeowner said he would call for final
|
ELE13-03380
| Permanent Service | 12/4/2013 | 12/5/2013 | 12/5/2013 6:09:23 PM | P | PASS |
|
|
Please call AT LEAST 1/2 hour before arriving on job site. Thanks! Phone #: ###-#### >> Inspection requested via web by PAUL PINNEY p/s u/g rec ok
|
ELE13-03380
| Electrical Rough-In | 12/5/2013 | 12/5/2013 | 12/5/2013 6:08:30 PM | P | FAIL |
|
|
Please call AT LEAST 1/2 hour before arriving on job site. Thanks! Phone #: ###-#### >> Inspection requested via web by PAUL PINNEY NEC 110.3 Manufacture requires GFEP protection for snow melt equipment
|
ELE13-03357
| Permanent Service | 12/4/2013 | 12/5/2013 | 12/5/2013 5:59:21 PM | P | FAIL |
|
|
We are upgrading the service on this home, I was hoping to get an inspection mid afternoon tomorrow so Idaho Power wont have any issues powering the home back up, please call for details, ###-####, thanks, Terry W. Phone #: ###-#### Phone #: ###-#### >> Inspection requested via web by Stephen Kren NEC 240.24 (A) service height. Overcurrent devices shall be readily accessible an shall be installed so that the center grip of the operating handle of the switch or breaker, when in its highest position,is not more than 6ft 7in. above floor or working platform.
|
ELE13-02606
| Final | 12/4/2013 | 12/5/2013 | 12/5/2013 2:07:40 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Celinda Winters final ok
|
ELE13-03060
| Final | 12/5/2013 | 12/5/2013 | 12/5/2013 1:25:37 PM | P | PASS |
|
|
Final of Walk-in cooler and freezer and rest of project Phone #: ###-#### >> Inspection requested via web by Stan Woodward final ok
|
ELE13-03382
| Electrical Rough-In | 12/5/2013 | 12/5/2013 | 12/5/2013 12:52:39 PM | P | PASS |
|
|
exterior lighting replacment Phone #: ###-#### >> Inspection requested via web by kendall bender CSA listed HID replacement fixtures, rough-in ok
|
ELE13-03049
| Electrical Rough-In | 12/5/2013 | 12/5/2013 | 12/5/2013 12:38:01 PM | P | PASS |
|
|
Wall cover. Dan on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen rough-in ok cover walls bathrooms, janitorial room, prep room. As per highlighted (yellow) and dated
|
ELE13-02942
| Electrical Rough-In | 12/4/2013 | 12/5/2013 | 12/5/2013 9:47:33 AM | A | PASS |
|
|
floor heat inspection Phone #: ###-#### >> Inspection requested via web by Barbara Szurgot rough-in ok cover floor heat
|
ELE13-03051
| Final | 12/4/2013 | 12/5/2013 | 12/5/2013 9:38:28 AM | A | PASS |
|
|
Owner Robert should be home thanks Phone #: ###-#### >> Inspection requested via web by Brad Baker final ok
|
ELE13-02902
| Final | 12/4/2013 | 12/5/2013 | 12/5/2013 9:07:47 AM | A | PASS |
|
|
Contact: Justin Hugo Phone #: ###-#### >> Inspection requested via web by Deb Gooden final ok
|
ELE13-03067
| Final | 12/3/2013 | 12/5/2013 | 12/5/2013 8:35:57 AM | A | NR |
|
|
Temporary Occupancy needed. Thank you! Phone #: ###-#### >> Inspection requested via web by Daniel Schaffeld Not ready, panel covers not installed
|
ELE13-03076
| Rough-In Permanent Service | 12/4/2013 | 12/5/2013 | 12/5/2013 8:22:43 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Heath Thomas rough-in p/s u/g n ok
|