PLM99-01750
| Plumbing Rough-in | 12/3/1999 | 12/6/1999 | 12/6/1999 12:00:00 AM | A | PASS |
|
|
Dave ###-#### South roof drains and partial R/I ok.
|
PLM99-04029
| Plumbing Rough-in | 12/3/1999 | 12/6/1999 | 12/6/1999 12:00:00 AM | A | PASS |
|
|
###-#### R/I ok.
|
PLM99-03840
| Water and/or Sewer | 12/3/1999 | 12/6/1999 | 12/6/1999 12:00:00 AM | A | PASS |
|
|
Bob ###-#### Sewer turn around final.
|
PLM99-03761
| Plumbing Rough-in | 12/6/1999 | 12/6/1999 | 12/6/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/06/1999 at 08:43:14. Contact: ###-####. R/I ok.
|
PLM99-04046
| Plumbing Rough-in | 12/3/1999 | 12/6/1999 | 12/6/1999 12:00:00 AM | P | PASS |
|
|
late pm ###-#### GW and R/I ok.
|
PLM99-04043
| Water Heater Final | 12/3/1999 | 12/6/1999 | 12/6/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/03/1999 at 12:51:59. Contact: ###-####. Water piping of relocated gas water heater final.
|