Inspections for the day of: Wednesday, December 6, 2006.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-01120 FIRE-Final Inspection12/5/200612/6/200612/6/2006 4:16:44 PMPPASS
Fire life safety is satisfactory.
FIR06-00309 INSP-Final Inspection12/5/200612/6/200612/6/2006 4:15:13 PMPPASS
Items on previous c/n have been completed, inspection passed.
FIR06-00863 INSP-Sprinkler Rough-in/Hydro12/6/200612/6/200612/6/2006 4:13:30 PMPPASS
Inspection requested was intended for fire alarm, not sprinkler rough-in as assigned. Fire alarm work is acceptable, inspection passed.
FIR06-00831 INSP-Final Inspection12/6/200612/6/200612/6/2006 3:22:51 PMPPASS
OH fire sprinkler final inspection passed, permit finaled.
FIR05-00271 INSP-Supply line flush12/6/200612/6/200612/6/2006 3:22:02 PMPPART
UG supply line flush completed.
FIR05-00270 INSP-Supply line flush12/6/200612/6/200612/6/2006 3:21:11 PMPPART
UG supply line flush completed.
FIR06-00087 INSP-Final Inspection11/28/200612/6/200612/6/2006 12:27:46 PMAPASS
Fire alarm inspection completed satisfactory, inspection passed, permit finaled.
FIR06-00927 INSP-Sprinkler Rough-in/Hydro12/5/200612/6/200612/6/2006 12:24:56 PMAPART
Approved for cover at the drop ceiling areas.
FIR06-00772 INSP-Sprinkler Rough-in/Hydro12/5/200612/6/200612/6/2006 10:19:28 AMAPART
UG fire supply line is approved for cover. Note: cover depth at planter to be verified for compliance as discussed.
BLD06-03000 FIRE-Final Inspection12/5/200612/6/200612/6/2006 10:01:20 AMAPASS
Fire life safety is satisfactory, inspection passed.
FIR06-00951 INSP-Final Inspection12/5/200612/6/200612/6/2006 10:00:33 AMAPASS
Fire alarm inspection passed, permit finaled.