ESC11-00333
| General Inspection | 12/6/2011 | 12/6/2011 | 12/12/2011 1:35:47 PM | | CANC |
|
|
|
ESC10-00878
| General Inspection | 12/6/2011 | 12/6/2011 | 12/6/2011 8:42:33 AM | | PART |
|
|
Site needs to be cleaned up on a daily basis.
|
ESC09-00470
| General Inspection | 12/6/2011 | 12/6/2011 | 12/6/2011 8:41:45 AM | | DONE |
|
|
No acitiy on the portion of land next to Warm Springs Ave. the rest of the site is in the vertical construction phase.
|
ESC10-00778
| General Inspection | 12/6/2011 | 12/6/2011 | 12/6/2011 8:08:21 AM | | PART |
|
|
Have began to shape stockpiles and will begin to screen piles in the near future. Have advised the RP; if the project becomes in active for more than 14 days they must temporary or perminately stabilize all disturbed that is in active per permit conditions and federal requirements.
|
ESC11-00156
| Aging Inspection | 12/6/2011 | 12/6/2011 | 12/6/2011 7:59:20 AM | | DONE |
|
|
NO activity seen at the present time.
|
ESC11-00141
| General Inspection | 12/6/2011 | 12/6/2011 | 12/6/2011 7:56:55 AM | | DONE |
|
|
Permit finaled.
|
ESC11-00141
| DOC - Permit Finaled | 12/6/2011 | 12/6/2011 | 12/6/2011 7:56:44 AM | P | PASS |
|
|
|