MEC17-05470
| Pressure Test | 12/6/2017 | 12/6/2017 | 12/6/2017 3:58:03 PM | P | PART |
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- 20lb gas pass- flues not under pressure
|
MEC17-05470
| Rough-in | 12/6/2017 | 12/6/2017 | 12/6/2017 3:57:27 PM | P | FAIL |
|
|
MEC Phone #: ###-#### Inspection requested via web by Oleg Chervak- insulation shield on b vent 2nd floor- combustion air basement-exhaust fan hooked up main level- manual J needs updated and resubbmitted to city on ducting and equipment-insulate all bare metal-dryer vent 2nd floor needs fixed smashed-flue test- upstair furnace closet needs combustion air and pan installed underneath-conditioned crawl fan and duct needs installed- fresh air to R/A plenum basement furnace- left correction notice with installer
|
MEC17-05149
| Rough-in | 12/5/2017 | 12/6/2017 | 12/6/2017 3:21:59 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- R/I ok-
|
MEC17-05149
| Pressure Test | 12/6/2017 | 12/6/2017 | 12/6/2017 3:21:32 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- 20lb gas pass
|
MEC17-04445
| Final | 12/6/2017 | 12/6/2017 | 12/6/2017 3:13:19 PM | P | PASS |
|
|
CLINT ###-#### MANUAL IN KITCHEN DRAWER Phone #: ###-#### Inspection requested via web by Jason Robinson
|
MEC17-04667
| Final | 12/6/2017 | 12/6/2017 | 12/6/2017 3:05:35 PM | P | PASS |
|
|
1:00- flue test ok
|
MEC17-05455
| Final | 12/5/2017 | 12/6/2017 | 12/6/2017 11:02:20 AM | A | PASS |
|
|
Please go as early as possible, thank! Call Max at ###-#### if you need anything. Inspection requested via web by Floyd Floyd Peek- work only entitled installing existing registers in new T grid ceiling- no new duct or flex installed- card signed
|
MEC17-05308
| Final | 11/30/2017 | 12/6/2017 | 12/6/2017 10:41:29 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Marisa Hone- all line set on roof need to be secured with approved hangers- need uv tape at unit on west side finished up to condenser
|
MEC17-04667
| Pressure Test | 12/5/2017 | 12/6/2017 | 12/6/2017 10:28:18 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Andrea Grigsby- need pressure test witnessed on flue- Furnace A/C and CO detectors ok
|
MEC17-05149
| Pressure Test | 12/5/2017 | 12/6/2017 | 12/6/2017 9:32:59 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- gauge wont zero out on gas line
|
MEC17-04747
| Final | 12/5/2017 | 12/6/2017 | 12/6/2017 8:37:17 AM | A | PART |
|
|
Charlotte Wilkes would prefer the earliest appointment please. Phone #: ###-#### Inspection requested via web by Rusty Karel- 20lb gas pass- will final permit out when mech permit for fireplace is issued
|
MEC17-00229
| Pressure Test | 12/6/2017 | 12/6/2017 | 12/6/2017 7:58:11 AM | A | CANC |
|
|
if possible can you be there between 8-830 as we will be there to meet u to perform the pressure test. Phone #: ###-#### >> Inspection requested via web by Marisa Hone Inspection cancelled from web by: Marisa Hone
|
MEC17-05462
| Pressure Test | 12/5/2017 | 12/6/2017 | 12/6/2017 12:00:00 AM | P | CANC |
|
|
***BUILDING PERMIT IS STILL IN REVIEW*** Please call Danny Phone #: ###-#### >> Inspection requested via web by Amanda Farnsworth
|