BLD17-00476
| FIRE-Final Inspection | 12/5/2017 | 12/6/2017 | 12/6/2017 2:05:51 PM | A | PASS |
|
|
Life fire safety inspection for this permit passed/complete.
|
BLD17-00472
| FIRE-Final Inspection | 12/5/2017 | 12/6/2017 | 12/6/2017 2:05:30 PM | A | PASS |
|
|
Life fire safety inspection for this permit passed/complete.
|
BLD17-00470
| FIRE-Final Inspection | 12/5/2017 | 12/6/2017 | 12/6/2017 2:05:08 PM | A | PASS |
|
|
Life fire safety inspection for this permit passed/complete.
|
FIR17-00678
| INSP-Sprinkler Rough-in | 12/5/2017 | 12/6/2017 | 12/6/2017 11:25:58 AM | A | PASS |
|
|
Rough to ocver inspection for area of work complete, area of work approved for cover. A fire sprinkler head will need to be added in the entry of the mens restroom, no fire sprinkler head at time of inspection (this area is out of the scope of work but is part of the tenant space). Fire sprinkler head will need to be added to pass life fire safety inspection at project completion.
|
BLD17-03798
| FIRE-Final Inspection | 12/5/2017 | 12/6/2017 | 12/6/2017 11:04:15 AM | A | FAIL |
|
|
Tried to call point of contact, Jeff Phone #: ###-####, phone number provided was not for point of contact. Went to space to see if it was open, space was locked with no access, life fire safety inspection will need to be rescheduled.
|
FIR17-00267
| INSP-Sprinkler Rough-in | 12/5/2017 | 12/6/2017 | 12/6/2017 10:47:10 AM | A | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 5 east of room 511 complete, rooms east of 511 on level 5 approved for cover with exception to room 512, room 512 will be inspected at a later date.
|
FIR17-00393
| INSP-Sprinkler Rough-in/Hydro | 12/5/2017 | 12/6/2017 | 12/6/2017 10:28:17 AM | A | FAIL |
|
|
Overhead fire sprinkler system lost 3 pounds in an hour and a half, overhead will need to be re-hydro tested.
|
FIR17-00623
| INSP-Final Inspection | 12/5/2017 | 12/6/2017 | 12/6/2017 10:18:00 AM | A | PART |
|
|
Partial final inspection complete for fire sprinklers in area of work passed/complete. Northwest corridor (part of core and shell) has dry type fire sprinkler heads that are supplied from the coffee shop side, dry heads to be installed before coffee shop completion. Dry sprinkler head piping install will be verified at life fire safety inspection.
|
FIR17-00655
| INSP-Final Inspection | 12/6/2017 | 12/6/2017 | 12/6/2017 10:14:15 AM | A | PART |
|
|
Final inspection for fire alarms in area of work passed/complete. Fire alarm permit will remain in issued status until core and shell is complete.
|
FIR17-00665
| INSP-Final Inspection | 12/6/2017 | 12/6/2017 | 12/6/2017 10:12:22 AM | A | CANC |
|
|
|
FIR17-00655
| INSP-Alarm Testing | 12/5/2017 | 12/6/2017 | 12/6/2017 10:11:11 AM | A | DONE |
|
|
Fire alarm testing complete.
|
FIR17-00649
| INSP-Final Inspection | 12/4/2017 | 12/6/2017 | 12/5/2017 12:41:47 PM | P | CANC |
|
|
Inspecting Technician: Ray McQueen Building Access: open 0900 - 1900 Phone #: ###-#### >> Inspection requested via web by Rose Peterson Inspection cancelled from web by: Rose Peterson
|