Inspections for the day of: Tuesday, December 7, 2010.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD09-02230 BLD-Aging Inspection12/7/201012/7/201012/7/2010 4:42:12 PM DONE
Job still in foundation stage, no new work to date.
BLD07-01602 BLD-Aging Inspection12/7/201012/7/201012/7/2010 4:41:38 PM PEND
BLD07-01600 BLD-Aging Inspection12/7/201012/7/201012/7/2010 4:41:23 PM PEND
BLD07-01599 BLD-Aging Inspection12/7/201012/7/201012/7/2010 4:41:10 PM PEND
BLD07-01597 BLD-Aging Inspection12/7/201012/7/201012/7/2010 4:41:00 PM PEND
BLD07-01596 BLD-Aging Inspection12/7/201012/7/201012/7/2010 4:40:47 PM PEND
BLD10-00988 BLD-Final12/6/201012/7/201012/7/2010 4:40:34 PMPPART
andy Phone #: ###-####. Ok for temp. occ. Need final letter from special inspection agency.
BLD10-02528 BLD-Final12/6/201012/7/201012/7/2010 2:28:41 PMPPASS
Call for better directions--Mike Phone #: ###-####. Public works has finaled.
BLD10-02528 DOC - Permit Finaled12/7/201012/7/201012/7/2010 2:28:17 PMPPASS
ESC09-00285 Aging Inspection12/7/201012/7/201012/7/2010 2:22:16 PM PASS
exterrior work and vertical construction has been completed. Homeowner is doing finish work on interior.
BLD10-02086 BLD-Final12/7/201012/7/201012/7/2010 2:05:38 PMPPASS
SID Phone #: ###-####. ok for perm occ.
ESC10-00770 BMP Violation12/7/201012/7/201012/7/2010 1:38:17 PMPPART
ESC permit sign is posted. Needs to provide drain inlet protection in parkinglot. RP was notified.
BLD10-02374 BLD-Framing/Rough-in12/6/201012/7/201012/7/2010 1:35:55 PMPPASS
robert Phone #: ###-####. Interior wood framed walls for phse 1 ok.
ESC10-00755 Random Inspection12/7/201012/7/201012/7/2010 10:04:19 AMAPASS
BLD10-02337 BLD-Framing/Rough-in12/6/201012/7/201012/7/2010 10:03:57 AMAPASS
Jim Phone #: ###-####. All framing issues have been resolved. Airseal completed and exterior house wrap being installed when on site. ok to insulate.
ESC10-00816 Site Final12/7/201012/7/201012/7/2010 9:44:05 AMADONE
ESC10-00816 DOC - Permit Finaled12/7/201012/7/201012/7/2010 9:43:47 AMPPASS
BLD10-01964 BLD-Final12/6/201012/7/201012/7/2010 9:43:26 AMAPASS
greg Phone #: ###-####
BLD10-01964 DOC - Permit Finaled12/7/201012/7/201012/7/2010 9:42:56 AMPPASS
Letter of compliance was issued. Additional plumbing and building permits will be required when owner decides to complete the bathroom, only underground has been completed in this phase.