Inspections for the day of: Monday, December 8, 2003.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRick Jackson
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR03-00356 FIR-Aging Inspection12/8/200312/8/200312/8/2003 12:00:00 AM PASS
the building is still under construction 12/8/2003 7:11:43 AM
FIR03-00468 FIR-Aging Inspection12/8/200312/8/200312/8/2003 12:00:00 AM PASS
this project is still ongoing 12/8/2003 12:54:54 PM
FIR03-00280 INSP-Final Inspection12/4/200312/8/200312/8/2003 12:00:00 AMAPASS
GRANTS CELL NUMBER
; Phone #: ###-#### Internet Inspection Request from: Terry Owsley
FIR03-00425 INSP-Sprinkler Rough-in/Hydro12/5/200312/8/200312/8/2003 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 12/5/2003 at 4:18:05 PM. will need the remote area (restrooms) recalc'd per Bill Alexander as there are more heads than shown on plans; provide as-builts for the changes made to DJ area and restrooms; add head gaurds for heads under stairs; heads obstructed/overspaced by ductwork at new bar on first floor under another FIR permit 12/8/2003 10:13:01 AM
FIR01-00126 INSP-Final Inspection12/5/200312/8/200312/8/2003 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 12/5/2003 at 4:30:50 PM. Contact: ###-####.
FIR01-00152 INSP-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMAPASS
BLD01-00027 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMAPASS
BLD02-01067 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/8/2003 at 10:31:48 AM. Contact: ###-####.
BLD03-01677 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/8/2003 at 10:32:24 AM. Contact: ###-####.
BLD02-01066 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/8/2003 at 10:32:58 AM. Contact: ###-####.
BLD02-01062 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/8/2003 at 10:34:10 AM. Contact: ###-####.
BLD02-02713 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/8/2003 at 10:34:50 AM. Contact: ###-####.
BLD02-02889 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/8/2003 at 11:16:50 AM. Contact: ###-####.
BLD03-01676 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
FIR03-00271 INSP-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
FIR03-00510 INSP-Final Inspection12/5/200312/8/200312/8/2003 12:00:00 AMPNR
billy; Phone #: ###-#### Internet Inspection Request from: Darla Downs electrician not ready; will reschedule for a later date 12/8/2003 2:47:42 PM
FIR03-00347 INSP-Sprinkler Rough-in/Hydro12/8/200312/8/200312/8/2003 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 12/8/2003 at 7:42:59 AM. hydro on new system okay; will need drain signage; need hanger on branch line in mechanical near kitchen; tie-in not complete and will verify at final;need escutcheons 12/8/2003 4:19:50 PM
FIR03-00629 INSP-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/8/2003 at 7:45:57 AM.
BLD02-02853 FIRE-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPART
###-#### larry phased project: okay to occupy the second floor on the north side 12/8/2003 2:48:48 PM
FIR02-00477 INSP-Final Inspection12/8/200312/8/200312/8/2003 12:00:00 AMPPASS