BLD08-01007
| FIRE-Final Inspection | 12/5/2008 | 12/8/2008 | 12/12/2008 3:16:58 PM | A | CANC |
|
|
Waiting on confermation that an agreement has been reached with the fire dept.
|
BLD07-02644
| FIRE-Conference | 12/8/2008 | 12/8/2008 | 12/8/2008 4:20:14 PM | P | DONE |
|
|
I went over life safety requirements for this project. It appears per the fire review comments that a fire hydrant was to be installed out front and fire sprinklers/alarm systems were to be installed as well. These items have not been installed. Scott and Sam have been contacted.
|
BLD08-02329
| FIRE-Final Inspection | 12/8/2008 | 12/8/2008 | 12/8/2008 4:18:11 PM | P | FAIL |
|
|
Sprinkler protection is required under the new overhead doors. All other items are ok.
|
FIR08-00006
| INSP-Final Inspection | 12/5/2008 | 12/8/2008 | 12/8/2008 3:27:04 PM | P | FAIL |
|
|
This inspection turned into a first floor walk through/conference. All of the first floor wing smoke detectors are overspaced, a smoke detector in the common are needs to be relocated closer to the double doors to the wing and visuals are overspaced. Locations are marked on the plans. No testing was performed.
|
FIR08-00798
| INSP-Final Inspection | 12/8/2008 | 12/8/2008 | 12/8/2008 1:37:06 PM | P | PASS |
|
|
Permit finaled
|
FIR08-00726
| INSP-Final Inspection | 12/8/2008 | 12/8/2008 | 12/8/2008 1:34:31 PM | P | PASS |
|
|
permit finaled
|
FIR08-00755
| INSP-Sprinkler Rough-in/Hydro | 12/5/2008 | 12/8/2008 | 12/8/2008 11:58:35 AM | A | PASS |
|
|
The underground supply piping is ok to cover but the piping layout does not match the city approved print. The changes will need to be reflected on the overhead piping layout and hydraulic calculations prior to final inspection.
|
BLD08-02242
| FIRE-Final Inspection | 12/5/2008 | 12/8/2008 | 12/8/2008 11:06:35 AM | A | FAIL |
|
|
Still need the dead bolt removed from the gate to the basement and a "Door to remain unlocked while the building is occupied" sticker at the exit as per the original correction notice.
|
FIR08-00798
| INSP-Sprinkler Rough-in/Hydro | 12/5/2008 | 12/8/2008 | 12/8/2008 10:21:19 AM | A | PASS |
|
|
Rough-in inspection passed.
|
FIR08-00726
| INSP-Sprinkler Rough-in/Hydro | 12/5/2008 | 12/8/2008 | 12/8/2008 10:19:54 AM | A | PASS |
|
|
Rough-in inspection passed
|
FIR08-00626
| INSP-Supply line flush | 12/5/2008 | 12/8/2008 | 12/8/2008 10:17:44 AM | A | PART |
|
|
The flush for the underground supply line passed but the supply line for the remote FDC has not been flushed as required.
|