Inspections for the day of: Thursday, December 8, 2016.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-01387 FIRE-Final Inspection12/8/201612/8/201612/8/2016 1:32:56 PMPFAIL
need to repair the exit discharge lights and clear the fire dept access
BLD16-01386 FIRE-Final Inspection12/8/201612/8/201612/8/2016 1:32:25 PMPPASS
life safety passed
BLD16-04262 FIRE-Final Inspection12/7/201612/8/201612/8/2016 1:31:45 PMAPASS
Exit signs and emergency lights have been repaired, hood suppression system is tagged, fire extinguishers (includeing K) are tagged, fire sprinkler system tagged, Per Barnie with State Fire the fire alarm system is inspected and fully functional including monitoring. He is going to email the documents to me. Life safety passed
FIR16-00540 INSP-Final Inspection12/7/201612/8/201612/8/2016 1:29:11 PMACANC
Cancel per Colton Phone #: ###-####
FIR16-00299 INSP-Sprinkler Rough-in12/7/201612/8/201612/8/2016 1:28:51 PMACANC
To be rescheduled for tomorrow morning per Jim and Perly
FIR16-00722 INSP-Sprinkler Rough-in12/7/201612/8/201612/8/2016 11:08:15 AMAPART
Rough-in passed and tenting passed and piping can be covered except for the riser room ceiling where the tenting was not complete.
FIR16-00284 INSP-Sprinkler Rough-in12/7/201612/8/201612/8/2016 9:35:32 AMAPART
The two apartments at the north end of the second floor that had tenting issues are ok to cover. Also the third floor north single apartment is now ok to cover. See the city approved plans for locations marked.
BLD16-02122 FIRE-Final Inspection12/7/201612/8/201612/8/2016 7:53:35 AMAPASS
life safety passed
BLD16-00766 FIRE-Supply Line Hydro12/7/201612/8/201612/8/2016 7:28:08 AMAPASS
Life safety passed