BLD98-02401
| INSP - Energy code compliance | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | A | PASS |
|
|
|
BLD98-02401
| INSP - Framing/Rough-in | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | A | PASS |
|
|
|
BLD98-02402
| INSP - Energy code compliance | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | A | PASS |
|
|
|
BLD98-02402
| INSP - Framing/Rough-in | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | A | PASS |
|
|
ok
|
BLD98-02608
| INSP - Final | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | P | PASS |
|
|
TIM ###-#### DIGIGAL PAGER RE-INSP FN l/c issued
|
BLD98-02707
| INSP - Final | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | P | PASS |
|
|
Took for Wes...l/c issued.
|
BLD98-02852
| INSP - Final | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | P | PASS |
|
|
BILL ###-#### FIANL INSP lc issued
|
BLD98-03411
| INSP - Framing/Rough-in | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | P | PART |
|
|
Conf. w/ bldr re shear panels, insp process; need truss manuf's ok for alteration of spacing trusses & adding purlins
|
BLD98-03453
| INSP - Framing/Rough-in | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | P | PART |
|
|
RANDY ###-#### SHEAR WALL; no approved plan...nailing appears ok
|
BLD98-03758
| INSP - Concrete | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | P | PART |
|
|
beam and bearing footings; rec'd resubmittal for floor beams...rejected Tom Cory's "chart" for sizing beams, re-calc'd beams and req'd additional footing size, marked plan: 3 9.5 ML's at 14' span; 2 9.5 ML's at 10' span...add 18"x 18"x 10" ftgs.
|
MEC98-03894
| INSP - Framing/ Rough-in | 12/9/1998 | 12/9/1998 | 12/9/1998 12:00:00 AM | P | PART |
|
|
gas test ok, complete ducts etc, flue ok
|