MEC08-03524
| Final | 12/8/2008 | 12/9/2008 | 12/9/2008 4:41:59 PM | P | PASS |
|
|
Please inspect as late in the afternoon as possible. Call with any problems. Thanks, April. Phone #: ###-#### Internet Inspection Request from: April Sims
|
ESC08-00800
| Random Inspection | 12/9/2008 | 12/9/2008 | 12/9/2008 4:22:51 PM | P | PASS |
|
|
talked to rp about piles of concrete
|
MEC08-02545
| Final | 12/9/2008 | 12/9/2008 | 12/9/2008 4:05:38 PM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Josh Blake
|
MEC08-03518
| Final | 12/8/2008 | 12/9/2008 | 12/9/2008 3:34:51 PM | P | PASS |
|
|
jarod is the installer on this job his # is ###-#### and he is installing today. Thank you Phone #: ###-#### Internet Inspection Request from: Veronica Shipley
|
MEC08-03531
| Final | 12/9/2008 | 12/9/2008 | 12/9/2008 3:19:04 PM | P | PASS |
|
|
|
MEC08-03531
| Pressure Test | 12/9/2008 | 12/9/2008 | 12/9/2008 3:18:47 PM | P | PASS |
|
|
CLAY - late afternoon please Phone #: ###-####
|
MEC08-03515
| Pressure Test | 12/9/2008 | 12/9/2008 | 12/9/2008 2:43:14 PM | P | PASS |
|
|
matt Phone #: ###-####---20LB OK
|
MEC07-03507
| Conference | 12/5/2008 | 12/9/2008 | 12/9/2008 12:47:25 PM | P | PEND |
|
|
meet with super at job to discuss over-hang at flue terminations and boiler that isn't installed yet in basement
|
MEC08-02784
| Final | 12/8/2008 | 12/9/2008 | 12/9/2008 11:37:04 AM | A | NR |
|
|
vladimir Phone #: ###-####---NEED A R/I
|
MEC08-02784
| Pressure Test | 12/9/2008 | 12/9/2008 | 12/9/2008 11:36:36 AM | A | PASS |
|
|
20LB GAS OK
|
MEC08-02317
| Final | 12/8/2008 | 12/9/2008 | 12/9/2008 11:34:54 AM | A | PASS |
|
|
Steve Przybos will be contact. First thing in the morning please. Tony Young will be doing final building sometime mid-morning. Thanks! Phone #: ###-#### Internet Inspection Request from: Wayne Van Cleave
|
MEC08-02468
| Final | 12/8/2008 | 12/9/2008 | 12/9/2008 10:13:59 AM | A | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Doug worden
|