Inspections for the day of: Tuesday, December 9, 2008.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDixie Fellows
TitleMEC-COM/RES INSPECTOR
Phone #794-6208
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC08-03524 Final12/8/200812/9/200812/9/2008 4:41:59 PMPPASS
Please inspect as late in the afternoon as possible. Call with any problems. Thanks, April.
Phone #: ###-#### Internet Inspection Request from: April Sims
ESC08-00800 Random Inspection12/9/200812/9/200812/9/2008 4:22:51 PMPPASS
talked to rp about piles of concrete
MEC08-02545 Final12/9/200812/9/200812/9/2008 4:05:38 PMPPASS
Phone #: ###-#### Internet Inspection Request from: Josh Blake
MEC08-03518 Final12/8/200812/9/200812/9/2008 3:34:51 PMPPASS
jarod is the installer on this job his # is ###-#### and he is installing today. Thank you Phone #: ###-#### Internet Inspection Request from: Veronica Shipley
MEC08-03531 Final12/9/200812/9/200812/9/2008 3:19:04 PMPPASS
MEC08-03531 Pressure Test12/9/200812/9/200812/9/2008 3:18:47 PMPPASS
CLAY - late afternoon please Phone #: ###-####
MEC08-03515 Pressure Test12/9/200812/9/200812/9/2008 2:43:14 PMPPASS
matt Phone #: ###-####---20LB OK
MEC07-03507 Conference12/5/200812/9/200812/9/2008 12:47:25 PMPPEND
meet with super at job to discuss over-hang at flue terminations and boiler that isn't installed yet in basement
MEC08-02784 Final12/8/200812/9/200812/9/2008 11:37:04 AMANR
vladimir Phone #: ###-####---NEED A R/I
MEC08-02784 Pressure Test12/9/200812/9/200812/9/2008 11:36:36 AMAPASS
20LB GAS OK
MEC08-02317 Final12/8/200812/9/200812/9/2008 11:34:54 AMAPASS
Steve Przybos will be contact. First thing in the morning please. Tony Young will be doing final building sometime mid-morning. Thanks! Phone #: ###-#### Internet Inspection Request from: Wayne Van Cleave
MEC08-02468 Final12/8/200812/9/200812/9/2008 10:13:59 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Doug worden