Inspections for the day of: Wednesday, December 9, 2009.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00686 INSP-Final Inspection12/9/200912/9/200912/11/2009 9:31:57 AMPPASS
Permit finaled
FIR09-00656 INSP-Sprinkler Rough-in/Hydro12/8/200912/9/200912/9/2009 3:48:36 PMPPART
The sprinkler piping in the new tenant space can be covered. The new upright sprinkler heads in the adjoining spaces is not yet complete.
FIR09-00110 INSP-Final Inspection12/8/200912/9/200912/9/2009 3:47:27 PMPCANC
Cancelled per Guy. To be rescheduled.
FIR09-00016 INSP-Final Inspection12/8/200912/9/200912/9/2009 3:47:09 PMPCANC
Cancelled per Guy. To be rescheduled.
FIR09-00082 INSP-Final Inspection12/8/200912/9/200912/9/2009 3:46:49 PMPCANC
Cancelled per Guy. To be rescheduled.
FIR09-00190 INSP-Final Inspection12/8/200912/9/200912/9/2009 3:45:52 PMPFAIL
The Netcon was 0. Need to provide as-built with information on the Intella-tap and provide two copies at the re-inspection. The bottom tamper switch did not operate.
FIR09-00228 INSP-Final Inspection12/8/200912/9/200912/9/2009 3:43:58 PMPFAIL
Netcon rating 0. The top tamper switch did not operate. Also the correct address is not being used. The address at the monitoring station was for a project on Explorer Drive which is three miles away. I stated that this item needs corrected immediately.
FIR09-00113 INSP-Final Inspection12/8/200912/9/200912/9/2009 3:38:28 PMPFAIL
The Netcon was a 0. Problem is there are bare wires inside the panel. Also trouble signals were reported on the panel as supervisory and sent to the monitoring station as supervisory.
FIR09-00349 INSP-Final Inspection12/8/200912/9/200912/9/2009 3:31:20 PMPFAIL
No inspection was started since the Netcon was only a 6. No other items inspected.