Inspections for the day of: Friday, December 9, 2011.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD11-01251 FIRE-Final Inspection12/8/201112/9/201112/9/2011 3:15:29 PMAPART
The east side remodeled area life safety is passed.
FIR11-00371 INSP-Sprinkler Rough-in12/9/201112/9/201112/9/2011 3:15:03 PMPPASS
Javier did not have the original copies of the approved plans. I let him know I will need them for the next inspection. I did however mark the copies he had the areas where sprinkler piping can be covered.
FIR11-00607 INSP-Supply line flush12/9/201112/9/201112/9/2011 2:51:07 PMPPASS
The underground supply piping is ok to cover. No flush was performed.
BLD11-02904 FIRE-Final Inspection12/9/201112/9/201112/9/2011 2:49:58 PMPPASS
life safety passed
FIR11-00435 INSP-Sprinkler Rough-in12/8/201112/9/201112/9/2011 2:31:20 PMACANC
Wrong permit called in for inspection. The fire sprinkler was intended.
FIR11-00464 INSP-Sprinkler Rough-in/Hydro12/8/201112/9/201112/9/2011 2:28:23 PMAPASS
Hydro test on overhead system passed.
FIR11-00555 INSP-Final Inspection12/6/201112/9/201112/9/2011 11:31:09 AMAFAIL
No actual testing of devices was performed due to no approved plans/notes on site. I noted one strobe overspaced and that two manual pull stations had been added at two exterior doors. As-builts are required prior to a final sign off.
FIR11-00297 INSP-Final Inspection12/8/201112/9/201112/9/2011 11:25:43 AMAFAIL
Still need the Building A devices display and report as Building A as per the original correction notice.
BLD11-02636 FIRE-Final Inspection12/9/201112/9/201112/9/2011 10:43:06 AMPPASS
Life safety passed.
FIR11-00656 INSP-Final Inspection12/8/201112/9/201112/9/2011 10:03:50 AMAPASS
permit finaled.Hood suppression system functioned correctly