ELE16-03987
| Electrical Rough-In | 12/8/2016 | 12/9/2016 | 12/9/2016 12:52:10 PM | P | PASS |
|
|
Inspection for sheet rock cover. I will not be there, but the General contractor will be there. His name is Dan, ###-#### Thank you Phone #: ###-#### Inspection requested via web by Lonnie Sorichta Rough in stair way area only rough in ok ok
|
ELE16-01770
| Final | 12/8/2016 | 12/9/2016 | 12/9/2016 12:42:54 PM | P | PART |
|
|
I would like to schedule final inspection for phase one of the project (upstairs and downstairs). I would like to schedule rough-in inspection for the main floor and phase two. Thanks so much for your time. Phone #: ###-#### Inspection requested via web by Dale Hinman Up beds and down area final only ok
|
ELE16-01770
| Electrical Rough-In | 12/9/2016 | 12/9/2016 | 12/9/2016 12:42:22 PM | P | PASS |
|
|
I would like to schedule final inspection for phase one of the project (upstairs and downstairs). I would like to schedule rough-in inspection for the main floor and phase two. Thanks so much for your time. Phone #: ###-#### Inspection requested via web by Dale Hinman Need to make sure junction oxes in attic are secured and blanked. Also owner was going to add 1 recep on counter left of oven. Kitchen area only ok to cover
|
ELE16-03632
| Final | 12/9/2016 | 12/9/2016 | 12/9/2016 12:07:35 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Shannon Wall Solar only Final ok
|
ELE16-03116
| Permanent Service | 12/9/2016 | 12/9/2016 | 12/9/2016 12:01:15 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Lee VanSchoiack p/s u/g n ok
|
ELE16-03337
| Final | 12/8/2016 | 12/9/2016 | 12/9/2016 11:41:03 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Final ok
|
ELE16-03669
| Final | 12/8/2016 | 12/9/2016 | 12/9/2016 10:56:20 AM | A | PASS |
|
|
Will call in the morning to schedule a time to meet you onsite. Phone #: ###-#### Inspection requested via web by Matthew Dunay Final ok
|
ELE16-03985
| Electrical Rough-In | 12/8/2016 | 12/9/2016 | 12/9/2016 9:26:32 AM | A | PASS |
|
|
Altenergy contact Jesse ###-####. Phone #: ###-#### Inspection requested via web by Andy Derrick Rough in ok
|
ELE16-03989
| Final | 12/9/2016 | 12/9/2016 | 12/9/2016 9:26:09 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Randy Fletcher Inspection cancelled from web by: Randy Fletcher
|
ELE16-03985
| Final | 12/9/2016 | 12/9/2016 | 12/9/2016 9:25:51 AM | P | PASS |
|
|
Altenergy contact Jesse ###-####. Phone #: ###-#### Inspection requested via web by Andy Derrick Final ok
|
ELE16-03669
| Electrical Rough-In | 12/9/2016 | 12/9/2016 | 12/9/2016 9:25:21 AM | P | PASS |
|
|
Will call in the morning to schedule a time to meet you onsite. Phone #: ###-#### Inspection requested via web by Matthew Dunay Solar rough in only ok
|
ELE16-03986
| Electrical Rough-In | 12/8/2016 | 12/9/2016 | 12/9/2016 9:24:05 AM | A | PASS |
|
|
This is for underground. If you have any questions please call Clay ###-#### Phone #: ###-#### Inspection requested via web by Clay Morgan Underground from house to garage only ok to cover
|