FIR16-00782
| INSP-Final Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 4:39:45 PM | P | PASS |
|
|
Final fire sprinkler inspection passed/complete
|
BLD14-03070
| FIRE-Final Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 4:05:31 PM | P | CANC |
|
|
Inspection request rescheduled.
|
FIR16-00251
| INSP-Final Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 3:47:50 PM | P | FAIL |
|
|
No document cabinet by fire panel, wall between storage rooms 2 and 3 has been removed, verified removal on city approved structural drawings, room is designated as "Social Room", social room needs an audio/visual device added per code requirement, device addition will require a resubmittal. Audio/visual devices did not latch into alarm during waterflow, when flow was stopped audio/visuals silenced without command. A knox box will be required due to the building having a monitored fire alarm system. Mens restroom has what appears to be a shower that is not complete, audio visual device needs to be changed to a weather proof type device.
|
FIR16-00052
| INSP-Sprinkler Rough-in | 12/7/2016 | 12/9/2016 | 12/9/2016 3:34:23 PM | P | FAIL |
|
|
No fire sprinkler installed in riser room, heads need to be installed for room protection. No head box/extra heads in riser room, additonal cover for underground supply has not been added, additional soil needs to be added for proper cover as noted before. Fire sprinkler backflow does no have a current inspection tag, backlow needs to be tested and tagged by a licensed backflow tester. Fire sprinkler head next to heater unit in "Future Kitchen" area needs to be changed to a high temp head due to how close the head is to the ceiling mounted heater.
|
FIR16-00052
| INSP-Final Inspection | 12/7/2016 | 12/9/2016 | 12/9/2016 3:27:53 PM | P | CANC |
|
|
Inspection request is for a final, this request cancelled.
|
BLD16-04305
| FIRE-Final Inspection | 12/7/2016 | 12/9/2016 | 12/9/2016 2:10:54 PM | A | PASS |
|
|
Previously notated items have been repaired/addressed, final life fire safety inspection passed/complete.
|
FIR16-00584
| INSP-Final Inspection | 12/8/2016 | 12/9/2016 | 12/9/2016 1:41:12 PM | A | PASS |
|
|
Final fire alarm inspection passed/complete
|
FIR16-00167
| INSP-Final Inspection | 12/8/2016 | 12/9/2016 | 12/9/2016 1:39:37 PM | A | PASS |
|
|
Final fire alarm inspection passed/complete
|
FIR16-00565
| INSP-Final Inspection | 12/8/2016 | 12/9/2016 | 12/9/2016 11:43:37 AM | A | PASS |
|
|
Final fire sprinkler inspection passed/complete
|
FIR16-00735
| INSP-Sprinkler Rough-in/Hydro | 12/8/2016 | 12/9/2016 | 12/9/2016 11:43:07 AM | A | PART |
|
|
Rough to cover inspection for hard lids complete, notated city approved drawings with red ink area's approved for cover.
|
FIR16-00535
| INSP-Supply line flush | 12/7/2016 | 12/9/2016 | 12/9/2016 11:37:55 AM | A | DONE |
|
|
Supply line flush complete
|
FIR16-00305
| INSP-Sprinkler Rough-in | 12/9/2016 | 12/9/2016 | 12/9/2016 10:00:19 AM | A | PART |
|
|
Partial rough to cover complete for level 1 parking area, cover approved from fire pump room to the east wall on level 1.
|
FIR16-00101
| INSP-Sprinkler Rough-in/Hydro | 12/8/2016 | 12/9/2016 | 12/9/2016 9:59:23 AM | A | PART |
|
|
Rough to cover inspection for sprinkler piping/sprinklers located in level 4 room entries complete, approved for cover.
|
BLD14-01827
| FIRE-Final Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 9:49:33 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
|
FIR16-00299
| INSP-Sprinkler Rough-in | 12/8/2016 | 12/9/2016 | 12/9/2016 9:16:59 AM | A | PART |
|
|
Rough in inspection complete for installed overhead fire sprinkler piping (wet systems only) complete for levels 1, 3, 4 and 5. A rough to cover inspection will need to be completed before cover.
|
BLD16-01452
| FIRE-Final Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 7:58:14 AM | A | PASS |
|
|
Short wall PIV in place and operational, final life fire safety inspection passed/complete.
|
FIR16-00540
| INSP-Final Inspection | 12/8/2016 | 12/9/2016 | 12/9/2016 7:41:42 AM | A | PASS |
|
|
Short wall mount PIV in place, operation verified. Final inspectio for fire sprinklers passed/complete.
|
FIR16-00773
| INSP-Sprinkler Rough-in | 12/8/2016 | 12/9/2016 | 12/9/2016 7:22:58 AM | A | PASS |
|
|
Rough in inspection complete for drop downs for future pendant heads in sandblast booths and under duct work heads complete.
|