Inspections for the day of: Friday, December 9, 2016.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00782 INSP-Final Inspection12/9/201612/9/201612/9/2016 4:39:45 PMPPASS
Final fire sprinkler inspection passed/complete
BLD14-03070 FIRE-Final Inspection12/9/201612/9/201612/9/2016 4:05:31 PMPCANC
Inspection request rescheduled.
FIR16-00251 INSP-Final Inspection12/9/201612/9/201612/9/2016 3:47:50 PMPFAIL
No document cabinet by fire panel, wall between storage rooms 2 and 3 has been removed, verified removal on city approved structural drawings, room is designated as "Social Room", social room needs an audio/visual device added per code requirement, device addition will require a resubmittal. Audio/visual devices did not latch into alarm during waterflow, when flow was stopped audio/visuals silenced without command. A knox box will be required due to the building having a monitored fire alarm system. Mens restroom has what appears to be a shower that is not complete, audio visual device needs to be changed to a weather proof type device.
FIR16-00052 INSP-Sprinkler Rough-in12/7/201612/9/201612/9/2016 3:34:23 PMPFAIL
No fire sprinkler installed in riser room, heads need to be installed for room protection. No head box/extra heads in riser room, additonal cover for underground supply has not been added, additional soil needs to be added for proper cover as noted before. Fire sprinkler backflow does no have a current inspection tag, backlow needs to be tested and tagged by a licensed backflow tester. Fire sprinkler head next to heater unit in "Future Kitchen" area needs to be changed to a high temp head due to how close the head is to the ceiling mounted heater.
FIR16-00052 INSP-Final Inspection12/7/201612/9/201612/9/2016 3:27:53 PMPCANC
Inspection request is for a final, this request cancelled.
BLD16-04305 FIRE-Final Inspection12/7/201612/9/201612/9/2016 2:10:54 PMAPASS
Previously notated items have been repaired/addressed, final life fire safety inspection passed/complete.
FIR16-00584 INSP-Final Inspection12/8/201612/9/201612/9/2016 1:41:12 PMAPASS
Final fire alarm inspection passed/complete
FIR16-00167 INSP-Final Inspection12/8/201612/9/201612/9/2016 1:39:37 PMAPASS
Final fire alarm inspection passed/complete
FIR16-00565 INSP-Final Inspection12/8/201612/9/201612/9/2016 11:43:37 AMAPASS
Final fire sprinkler inspection passed/complete
FIR16-00735 INSP-Sprinkler Rough-in/Hydro12/8/201612/9/201612/9/2016 11:43:07 AMAPART
Rough to cover inspection for hard lids complete, notated city approved drawings with red ink area's approved for cover.
FIR16-00535 INSP-Supply line flush12/7/201612/9/201612/9/2016 11:37:55 AMADONE
Supply line flush complete
FIR16-00305 INSP-Sprinkler Rough-in12/9/201612/9/201612/9/2016 10:00:19 AMAPART
Partial rough to cover complete for level 1 parking area, cover approved from fire pump room to the east wall on level 1.
FIR16-00101 INSP-Sprinkler Rough-in/Hydro12/8/201612/9/201612/9/2016 9:59:23 AMAPART
Rough to cover inspection for sprinkler piping/sprinklers located in level 4 room entries complete, approved for cover.
BLD14-01827 FIRE-Final Inspection12/9/201612/9/201612/9/2016 9:49:33 AMPCANC
Phone #: ###-#### >> Inspection requested via web by Corey Hockersmith Inspection cancelled from web by: Corey Hockersmith
FIR16-00299 INSP-Sprinkler Rough-in12/8/201612/9/201612/9/2016 9:16:59 AMAPART
Rough in inspection complete for installed overhead fire sprinkler piping (wet systems only) complete for levels 1, 3, 4 and 5. A rough to cover inspection will need to be completed before cover.
BLD16-01452 FIRE-Final Inspection12/9/201612/9/201612/9/2016 7:58:14 AMAPASS
Short wall PIV in place and operational, final life fire safety inspection passed/complete.
FIR16-00540 INSP-Final Inspection12/8/201612/9/201612/9/2016 7:41:42 AMAPASS
Short wall mount PIV in place, operation verified. Final inspectio for fire sprinklers passed/complete.
FIR16-00773 INSP-Sprinkler Rough-in12/8/201612/9/201612/9/2016 7:22:58 AMAPASS
Rough in inspection complete for drop downs for future pendant heads in sandblast booths and under duct work heads complete.