FIR18-00564
| INSP-Sprinkler Rough-in | 2/1/2019 | 2/1/2019 | 2/1/2019 2:35:27 PM | P | CANC |
|
|
No city approved plans on site, no inspetion. Johnathon Phone #: ###-####
|
FIR18-00565
| INSP-Sprinkler Rough-in | 2/1/2019 | 2/1/2019 | 2/1/2019 2:35:04 PM | P | CANC |
|
|
No city approved plans on site. No inspection. Johnathon Phone #: ###-####
|
FIR18-00675
| INSP-Sprinkler Rough-in/Hydro | 1/31/2019 | 2/1/2019 | 2/1/2019 2:34:35 PM | P | PASS |
|
|
See the city approved plans for locations in the south side of building where sprinkler piping can be covered. I also looked at the overhead sprinkler piping in the Kitchen/Cooler area. Another rough-in inspection will be needed for cover when the T-bar and pendants in this area have been installed. Right now it is just the supply piping at the roof deck.
Cesear Phone #: ###-####
|
FIR18-00675
| INSP-Supply line flush | 1/31/2019 | 2/1/2019 | 2/1/2019 1:30:10 PM | P | PASS |
|
|
Underground flush passed
Cesear Phone #: ###-####
|
NAF18-00086
| INSP-Sprinkler Rough-in | 2/1/2019 | 2/1/2019 | 2/1/2019 1:08:02 PM | P | PART |
|
|
No city approved plans/small documents on site. No inspection performed but we did talk about cover inspection procedure on the project.
|
FIR19-00070
| INSP-Final Inspection | 1/31/2019 | 2/1/2019 | 2/1/2019 10:52:28 AM | A | PASS |
|
|
permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
NAF18-00086
| INSP-Sprinkler Rough-in | 1/31/2019 | 2/1/2019 | 2/1/2019 10:34:39 AM | A | CANC |
|
|
Contact Andrew Larson - ###-#### 30 Min Prior to RTC Insp start please
Thank YOU, Teri Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
FIR17-00603
| INSP-Sprinkler Rough-in | 1/31/2019 | 2/1/2019 | 2/1/2019 9:59:32 AM | A | PASS |
|
|
See the city approved plans for location marked "ok" where sprinkler piping is ok for cover.
Todd Ketterling is your contact. Thanks for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR17-00626
| INSP-Alarm Testing | 1/30/2019 | 2/1/2019 | 2/1/2019 9:26:52 AM | A | FAIL |
|
|
The signals did go to the airport control as device and room number but the airport did not have an actual description of the location on site for the alarm. Gary is going to add description and reschedule.
Re-inspect after placing ARFF building on airport network - verification testing that new building reports to the Airport operations center. Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
FIR16-00810
| INSP-Final Inspection | 1/31/2019 | 2/1/2019 | 2/1/2019 8:24:50 AM | A | PASS |
|
|
permit finaled