Inspections for the day of: Wednesday, February 10, 2010.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD10-00192 FIRE-Final Inspection2/10/20102/10/20102/10/2010 3:44:33 PMPFAIL
Remove the round knob door hardware and provide singel action lever hardware, provide sticker, and mount the K class fire extinguisher off of the floor.
BLD09-01717 FIRE-Final Inspection2/9/20102/10/20102/10/2010 3:32:13 PMPCANC
Cancelled per Bill Phone #: ###-####
FIR09-00708 INSP-Sprinkler Rough-in2/10/20102/10/20102/10/2010 2:30:42 PMPPASS
The 24 hour air test on system 4 passed.
FIR10-00031 INSP-Sprinkler Rough-in2/9/20102/10/20102/10/2010 1:24:56 PMAPART
The sprinkler piping can be covered. I noted that two of the new extended coverage pendants at the Lobby are less than 8' apart. The solution will be verified at the final inspection. The riser also has a current inspection tag.
BLD09-00323 FIRE-Final Inspection2/9/20102/10/20102/10/2010 11:24:11 AMACANC
Wrong inspection type set up.
FIR09-00731 INSP-Supply line flush2/9/20102/10/20102/10/2010 10:41:33 AMAPASS
The underground supply line flush passed.
BLD10-00173 FIRE-Final Inspection2/9/20102/10/20102/10/2010 9:38:53 AMAFAIL
Provide singel action hardware on the rear exit door such as lever action or panic. Thumbturn locks are not allowed. Also the existing fire sprinkler system requires modifications to meet code requirements. This work requires a separate permit by a licensed fire sprinkler contractor.
BLD10-00173 FIRE-Hydro test above ground2/9/20102/10/20102/10/2010 9:37:04 AMACANC
Wrong inspection type set up.