ELE11-00558
| ELE-Aging Inspection | 2/10/2012 | 2/10/2012 | 2/10/2012 1:30:45 PM | | PASS |
|
|
contacted electrical contractor, He said he would call for final inspection
|
ELE12-00194
| Electrical Rough-In | 2/10/2012 | 2/10/2012 | 2/10/2012 1:20:46 PM | P | FAIL |
|
|
BOB Phone #: ###-#### NEC 110.14 Conductors of dissimilar metals shall not be intermixed in a terminal.NEC 215.12 Grounded conductor of a feeder shall be identified (green) Service feeders shall be protected from physical damage (ran in raceway,conduit)
|
GCE12-00017
| GCE-Rough-In Permanent Service | 2/9/2012 | 2/10/2012 | 2/10/2012 9:50:53 AM | A | PASS |
|
|
Daron @ ###-#### rough-in p/s u/g n ok
|
ELE11-01637
| Electrical Rough-In | 2/9/2012 | 2/10/2012 | 2/10/2012 9:08:00 AM | A | NR |
|
|
bert - 2nd floor - east wing Phone #: ###-####
|
ELE12-00279
| Final | 2/9/2012 | 2/10/2012 | 2/10/2012 8:42:14 AM | A | PASS |
|
|
John will take you around to look at all of the work we have done on three permits. Phone #: ###-#### >> Inspection requested via web by Kevin Perez final ok
|
ELE12-00104
| Final | 2/9/2012 | 2/10/2012 | 2/10/2012 8:40:11 AM | A | PASS |
|
|
John will take you around to look at all of the work we have done on three permits. Phone #: ###-#### >> Inspection requested via web by Kevin Perez final ok
|
ELE11-02795
| Final | 2/9/2012 | 2/10/2012 | 2/10/2012 8:36:48 AM | A | PASS |
|
|
John will take you around to look at all of the work we have done on three permits. Phone #: ###-#### >> Inspection requested via web by Kevin Perez final ok
|
ELE12-00021
| Electrical Rough-In | 2/9/2012 | 2/10/2012 | 2/10/2012 8:07:04 AM | A | PASS |
|
|
Cover inspection for ceiling Thanks Phone #: ###-#### >> Inspection requested via web by Lynn Cable rough-in ok cover ceiling grid
|
ESC11-00889
| General Inspection | 2/10/2012 | 2/10/2012 | | | |
|
|
|