FIR14-00889
| INSP-Sprinkler Rough-in | 2/10/2015 | 2/10/2015 | 2/10/2015 1:34:03 PM | P | PART |
|
|
Begin 24 hr air test of the dry system at 1:30PM @ 40psig.
|
FIR15-00051
| INSP-Sprinkler Rough-in | 2/9/2015 | 2/10/2015 | 2/10/2015 1:06:41 PM | P | PART |
|
|
Okay to cover overhead fire sprinkler work at the sheetrock lid ceilings as noted on approved plans.
|
BLD14-03282
| FIRE-Conference | 2/10/2015 | 2/10/2015 | 2/10/2015 12:50:54 PM | P | DONE |
|
|
On site visit regarding exiting requirements, door hardware, fire sprinkler, fire alarm and hood suppression permit work. Need to revise plans to show accurate existing door swing at the kitchen area service exit.
|
BLD14-03086
| FIRE-Final Inspection | 2/10/2015 | 2/10/2015 | 2/10/2015 10:32:35 AM | P | PASS |
|
|
Fire life safety finaled.
|
FIR15-00007
| INSP-Final Inspection | 2/9/2015 | 2/10/2015 | 2/10/2015 10:32:07 AM | A | PASS |
|
|
Scope of fire alarm work completed and passed inspection and testing. Permit finaled.
|
FIR14-00708
| INSP-Sprinkler Rough-in | 2/10/2015 | 2/10/2015 | | P | |
|
|
Rough to cover 2nd floor F. ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Carter II
|
FIR14-00681
| INSP-Sprinkler Rough-in/Hydro | 2/10/2015 | 2/10/2015 | | P | |
|
|
Partial rough to cover bldg D 1st floor (soffits/hard lids ) ###-#### Leroy >> Inspection requested via web by Scott Carter II
|
FIR14-00870
| INSP-Final Inspection | 2/5/2015 | 2/10/2015 | | P | |
|
|
Forrest, The school district would like to schedule the test for 3:30 on Tuesday if at all possible. Please let me know as soon as possible if that will work so I can confirm it with them. Thank you. Jason ###-#### Phone #: ###-#### >> Inspection requested via web by Jason Minnick
|