Inspections for the day of: Tuesday, February 10, 2015.
Number of inspections: 8
Percentage of inspections complete: 63 %
Percentage of inspections not complete: 38 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00889 INSP-Sprinkler Rough-in2/10/20152/10/20152/10/2015 1:34:03 PMPPART
Begin 24 hr air test of the dry system at 1:30PM @ 40psig.
FIR15-00051 INSP-Sprinkler Rough-in2/9/20152/10/20152/10/2015 1:06:41 PMPPART
Okay to cover overhead fire sprinkler work at the sheetrock lid ceilings as noted on approved plans.
BLD14-03282 FIRE-Conference2/10/20152/10/20152/10/2015 12:50:54 PMPDONE
On site visit regarding exiting requirements, door hardware, fire sprinkler, fire alarm and hood suppression permit work. Need to revise plans to show accurate existing door swing at the kitchen area service exit.
BLD14-03086 FIRE-Final Inspection2/10/20152/10/20152/10/2015 10:32:35 AMPPASS
Fire life safety finaled.
FIR15-00007 INSP-Final Inspection2/9/20152/10/20152/10/2015 10:32:07 AMAPASS
Scope of fire alarm work completed and passed inspection and testing. Permit finaled.
FIR14-00708 INSP-Sprinkler Rough-in2/10/20152/10/2015 P 
Rough to cover 2nd floor F. ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Carter II
FIR14-00681 INSP-Sprinkler Rough-in/Hydro2/10/20152/10/2015 P 
Partial rough to cover bldg D 1st floor (soffits/hard lids ) ###-#### Leroy >> Inspection requested via web by Scott Carter II
FIR14-00870 INSP-Final Inspection2/5/20152/10/2015 P 
Forrest, The school district would like to schedule the test for 3:30 on Tuesday if at all possible. Please let me know as soon as possible if that will work so I can confirm it with them. Thank you. Jason ###-#### Phone #: ###-#### >> Inspection requested via web by Jason Minnick