Inspections for the day of: Monday, February 10, 2020.
Number of inspections: 16
Percentage of inspections complete: 94 %
Percentage of inspections not complete: 6 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-04435 BLD-Framing/Rough-in2/3/20202/3/2020 P 
Charlie- framing walls for level G ( nothing to do with plan mod) Phone #: ###-####
BLD19-02359 BLD-Final2/10/20202/10/20202/10/2020 2:59:09 PMPPASS
Call Dan For access Phone #: ###-#### Inspection requested via web by Daniel Appel
BLD19-02359 DOC - Permit Finaled2/10/20202/10/20202/10/2020 2:58:59 PMPPASS
BLD19-03918 BLD-Concrete2/6/20202/10/20202/10/2020 2:58:41 PMPCANC
LVL 2 slab on deck pour - area "B" Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
BLD19-03918 BLD-Concrete2/7/20202/10/20202/10/2020 2:58:26 PMAPEND
Columns to be poured @ South half of pour "A". Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
BLD19-03918 BLD-Footing2/7/20202/10/20202/10/2020 2:58:02 PMAPEND
Apartment footings @ SW quadrant. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
BLD19-03852 BLD-Footing2/10/20202/10/20202/10/2020 2:22:06 PMPPASS
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD19-03428 BLD-Energy code compliance2/6/20202/10/20202/10/2020 1:25:56 PMPFAIL
Insulation guys are on for same day so later in the afternoon please. Phone #: ###-#### Inspection requested via web by Gus Brandon
BLD19-02688 BLD-Final2/7/20202/10/20202/10/2020 10:45:14 AMAPASS
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD19-02688 DOC - Permit Finaled2/10/20202/10/20202/10/2020 10:44:58 AMPPASS
BLD19-04333 BLD-Footing2/7/20202/10/20202/10/2020 10:44:01 AMAPASS
Chris Phone #: ###-####
BLD20-00083 BLD-Framing/Rough-in2/7/20202/10/20202/10/2020 9:39:46 AMAPASS
Mike Phone #: ###-####
BLD19-01727 BLD-Framing/Rough-in2/7/20202/10/20202/10/2020 9:23:52 AMANR
Grant Phone #: ###-####
BLD19-01622 BLD-Framing/Rough-in2/7/20202/10/20202/10/2020 9:23:40 AMAPASS
Phone #: ###-####
BLD19-04653 BLD-Ceiling Grid Inspection2/7/20202/10/20202/10/2020 8:50:01 AMAPASS
bruce Phone #: ###-####
BLD19-04955 DOC - Permit Finaled2/10/20202/10/20202/10/2020 6:53:54 AMAPASS