BLD96-02710
| INSP - Letter of compliance | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | | PASS |
|
|
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 13230
|
BLD96-02710
| INSP - Letter of compliance | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | | PASS |
|
|
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 13230
|
BLD96-02554
| INSP - Letter of compliance | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | | PASS |
|
|
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 13229
|
BLD96-02554
| INSP - Letter of compliance | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | | PASS |
|
|
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 13229
|
BLD96-03051
| INSP - Framing/Rough-in | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | | PASS |
|
|
/ / 301 - FRAM-OK FRAMING
|
BLD96-03120
| INSP - Final | 2/10/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | A | PASS |
|
|
02/11/97 301 - FINAL FOR C/O. TCO -TEMP C OF O ISSUED pending temp exit doors to be replaced. ì
|
BLD97-00006
| INSP - Energy code compliance | 2/10/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | A | PART |
|
|
02/11/97 301 - c/n not done.
|
BLD96-00488
| INSP - Final | 2/7/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | A | PART |
|
|
02/11/97 301 - FINAL FOR C/O. CORR-CORREC-CALL FOR REINSP WHEN COMPLETED OTH-OTHER AGENCIES NOT APPROVED
|
BLD96-02554
| INSP - Final | 2/10/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | A | PASS |
|
|
02/11/97 301 - FINAL REINSPECT FNL -OK FINAL
|
BLD96-00382
| INSP - Final | 2/10/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | CANC |
|
|
/ / 301 - cancled by owner
|
BLD96-01097
| INSP - Footings | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | PASS |
|
|
02/11/97 301 - FOOTINGS REBAR, ETC....... FDN -OK FOUNDATION
|
BLD96-03049
| INSP - Energy code compliance | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | PASS |
|
|
02/11/97 301 - INSL-OK INSULATION-ENERGY CODE
|
BLD96-03049
| INSP - Framing/Rough-in | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | FAIL |
|
|
02/11/97 301 - frame reinspect. CORR-CORREC-CALL FOR REINSP WHEN COMPLETED plumbing must be moved no ope w/in 5 ft roof.
|
BLD97-00041
| INSP - Framing/Rough-in | 2/10/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | NR |
|
|
02/11/97 301 - n/r
|
BLD97-00153
| INSP - Footings | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | PASS |
|
|
02/11/97 301 - FRMS-OK FORMS-REBAR set backs ok
|
BLD97-00250
| INSP - Footings | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | PASS |
|
|
02/11/97 301 - FDN -OK FOUNDATION
|
BLD96-03051
| INSP - Energy code compliance | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | PASS |
|
|
02/11/97 301 - INSL-OK INSULATION-ENERGY CODE
|
BLD96-02710
| INSP - Final | 2/11/1997 | 2/11/1997 | 2/11/1997 12:00:00 AM | P | PASS |
|
|
02/11/97 301 - FNL -OK FINAL
|