PLM99-00842
| Final | 2/10/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | A | FAIL |
|
|
###-#### Seal ejector lid, pipe water heater T&P to drain. 2/14/00 12:11:15 PM
|
PLM00-00045
| Groundwork | 2/10/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/10/2000 at 12:47:33. Contact: . FD in basement ok. 2/14/00 12:12:00 PM
|
PLM00-00362
| Plumbing Rough-in | 2/10/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | A | PASS |
|
|
###-#### R/I ok. 2/14/00 12:11:42 PM
|
PLM00-00228
| Final | 2/10/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 02/10/2000 at 14:57:23. Contact: ###-####. Interceptor UTR's ok, pour concrete prior to final. 2/14/00 12:11:34 PM
|
PLM99-03859
| Final | 2/10/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/10/2000 at 15:28:28. Contact: ###-####. Final ok. 2/14/00 12:12:06 PM
|
PLM00-00359
| Groundwork | 2/10/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 02/10/2000 at 15:30:42. Contact: ###-####. G/W ok. 2/14/00 12:11:50 PM
|
PLM00-00160
| Plumbing Rough-in | 2/11/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | A | PASS |
|
|
R/I ok.
|
PLM00-00200
| Water and/or Sewer | 2/11/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | P | PASS |
|
|
S/W ok.
|
PLM00-00260
| Plumbing Rough-in | 2/10/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 02/10/2000 at 16:56:37. Contact: ###-####. Sink relocation 2nd floor R/I ok. 2/14/00 12:10:47 PM
|
PLM00-00368
| Plumbing Rough-in | 2/11/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | P | PASS |
|
|
chris ###-#### r/i R/I ok. 2/14/00 12:10:08 PM
|
PLM99-04098
| Final | 2/11/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | P | PASS |
|
|
###-#### Final ok. 2/14/00 12:10:55 PM
|
PLM00-00245
| Plumbing Rough-in | 2/11/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | P | FAIL |
|
|
###-#### No tests on storm drain or sewer. 2/14/00 12:10:22 PM
|
PLM00-00247
| Plumbing Rough-in | 2/11/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | P | FAIL |
|
|
###-#### No tests on storm drain or sewer. 2/14/00 12:10:34 PM
|
PLM00-00376
| Water and/or Sewer | 2/11/2000 | 2/11/2000 | 2/11/2000 12:00:00 AM | P | PASS |
|
|
###-#### S/W final ok. 2/14/00 12:10:01 PM
|