BLD09-02071
| FIRE-Final Inspection | 2/10/2010 | 2/11/2010 | 2/12/2010 7:15:04 AM | P | PASS |
|
|
Life safety passed. Plans had not been routed through fire, hence the contractor had installed duct smoke detectors as shown on the city approved plans. They however had not been connected to the existing fire alarm system. Due to the hvac units being smaller than 2,000 cfm the duct smoke detectors have been removed.
|
FIR09-00536
| INSP-Sprinkler Rough-in | 2/11/2010 | 2/11/2010 | 2/11/2010 3:26:19 PM | P | CANC |
|
|
Cancelled due to time constraints and Micron plan review. I spoke to todd and the inspection will be rescheduled for tomorrow.
|
BLD09-00461
| FIRE-Final Inspection | 2/11/2010 | 2/11/2010 | 2/11/2010 3:22:03 PM | P | FAIL |
|
|
Per the approved drawings and documents the address is 4450. The address of 4420 has been installed on the building. I spoke to April with the addressing dept. and she believes that neither address is correct. I let the contractor know that he needs to speak to April to get the correct address. Also the exit discharge light out of the southeast exit did not work nor did the emergency light just inside of this same door. All other items appear ok.
|
FIR09-00692
| INSP-Final Inspection | 2/11/2010 | 2/11/2010 | 2/11/2010 1:13:46 PM | P | CANC |
|
|
Cancelled due to too many inspections, time constraints and Micron plan review. Inspection was originally scheduled for this morning but was changed to an afternoon. I spoke to the contractor about performing a morning inspection but he wanted an afternoon inspection. To be rescheduled for tomorrow.
|
FIR10-00053
| INSP-Final Inspection | 2/11/2010 | 2/11/2010 | 2/11/2010 12:20:10 PM | P | PASS |
|
|
permit finaled
|
BLD10-00035
| FIRE-Final Inspection | 2/10/2010 | 2/11/2010 | 2/11/2010 11:27:19 AM | A | FAIL |
|
|
Provide the flammable materials storage cabinets as per the city approved plans and provide storage height control as discussed.
|
BLD09-01219
| FIRE-Final Inspection | 2/11/2010 | 2/11/2010 | 2/11/2010 11:21:04 AM | P | PASS |
|
|
Life safety passed
|
FIR09-00720
| INSP-Final Inspection | 2/10/2010 | 2/11/2010 | 2/11/2010 11:20:00 AM | P | PASS |
|
|
Permit finaled. Bob Seagler is folowing up on the placement of the map at the facp.
|
FIR09-00735
| INSP-Final Inspection | 2/10/2010 | 2/11/2010 | 2/11/2010 11:11:54 AM | P | PASS |
|
|
permit finaled
|
FIR09-00708
| INSP-Sprinkler Rough-in/Hydro | 2/10/2010 | 2/11/2010 | 2/11/2010 10:24:40 AM | A | PASS |
|
|
The overhead hydro test of dry systems 3 and 4 and wet system 1 passed.
|
BLD09-01866
| FIRE-Final Inspection | 2/9/2010 | 2/11/2010 | 2/11/2010 9:36:26 AM | A | FAIL |
|
|
Provide an annual inspection for both of the fire extinguishers, provide the correct sticker at the main exit as discussed, post address numbers atleast 4" in height and provide passage hardware on the breakroom door since an exit sign is designating this door as an exit path.
|
FIR09-00716
| INSP-Final Inspection | 2/8/2010 | 2/11/2010 | 2/11/2010 9:06:46 AM | A | FAIL |
|
|
The NetCon was a 7 and the manual pull station had been installed above 48". No other testing was performed.
|
FIR09-00717
| INSP-Final Inspection | 2/8/2010 | 2/11/2010 | 2/11/2010 9:06:16 AM | A | FAIL |
|
|
The NetCon was a 6 and the manual pull station had been installed above 48". No other testing was performed.
|
FIR09-00692
| INSP-Final Inspection | 2/9/2010 | 2/11/2010 | 2/11/2010 7:33:24 AM | A | CANC |
|
|
I spoke to Tom and he stated that his office shoud be rescheduling for this afternoon.
|
FIR09-00720
| INSP-Final Inspection | 2/10/2010 | 2/11/2010 | 2/10/2010 10:13:32 AM | A | CANC |
|
|
Raef is the contact his no. is ###-####. Inspection requested from web by: Shawna Gates Phone #: ###-#### Inspection cancelled from web by: Shawna Gates
|