ESC14-01023
| Site Preparation | 2/10/2015 | 2/11/2015 | 2/11/2015 4:41:09 PM | P | PASS |
|
|
Monica Phone #: ###-####
Proper silt fence installation - trenched and backfilled. Sturdy tracking pad/rock entrance is provided, Permit sign clearly posted with contact details.
Gravel bag protect DIs currently. If inadequate or broken down, may consider witches hat filter bag or coir mat/coconut fiber inlet protection.
Approved for construction.
|
ESC14-00296
| General Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 4:28:31 PM | | PASS |
|
|
WIP. Crewmen working to keep down trackout. No dewatering commenced or reported. No corrections at this time.
|
ESC14-00299
| General Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 4:27:20 PM | | CANC |
|
|
rescheduled.
|
ESC14-00328
| General Inspection | 2/10/2015 | 2/11/2015 | 2/11/2015 2:07:21 PM | P | PASS |
|
|
No activity or equipment on site. Stockpiles have perimeter fiber wattles installed. Need to determine if project will resume in the Spring. No issues at site.
|
ESC15-00019
| Random Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 1:58:17 PM | P | PASS |
|
|
Limited activity at time of inspection. Got report that there was a muddy discharge downstream from Farmer Union intake area.
After further investigation it is clear that the turbid flow is coming from Crane Creek, not from this project.
|
ESC14-01151
| Random Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 11:22:32 AM | P | PART |
|
|
Limits of disturbance and silt fence perimeter are in good condition.
Now that conditions have dried out, need to sweep the street and parking areas where workers are parking and unloading. Lots of loose sediment.
|
ESC14-00360
| General Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 11:21:01 AM | | PASS |
|
|
WIP. Gutter has been cleaned. No issues at site. Near completion.
|
ESC14-00106
| General Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 11:11:21 AM | | PASS |
|
|
revegetating. Near full establishment.
|
ESC14-01044
| Random Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 11:09:03 AM | A | PASS |
|
|
Draco culdesac has been swept and workers are staying off the mud. Vegetated buffer has been preserved. No violations observed.
|
ESC14-00181
| Aging Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 10:54:19 AM | | PASS |
|
|
Home construction is complete. Work ongoing on detached garage. BLD open. Yard is not yet finished but loose dirt is surround by perimeter wattle. Approved.
|
ESC14-00496
| Aging Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 10:17:51 AM | | PART |
|
|
BMPs installed to protect storm drain system. Worker vehicles parking on hard surfaces, no significant trackout.
Correction:
Sweep up Grey Pine and Pine Nut and shovel/rake out clumpy mud areas next curbing. Dry weather window will be good time to get ahead of the next rain.
This house near completion, need to removed trash bin and clean gutter/driveway.
Called site supervisor Brian for correction.
|
ESC14-00494
| Aging Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 10:07:23 AM | | PASS |
|
|
Home complete, landscaped, and construction materials removed. Ongoing projects across street, so they will be continuing sweeping and cleanup.
|
ESC14-00494
| DOC - Permit Finaled | 2/11/2015 | 2/11/2015 | 2/11/2015 10:06:08 AM | P | PASS |
|
|
|
ESC14-00486
| Random Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 9:55:38 AM | A | PASS |
|
|
Carwash and vehicle display lot are near completion. Irrigation lines, landscaping, and site cleanup are in progress. No trash, trackout, or discharges around site. Auto Drive recently swept with no loose sediment accumulations.
Parking lot is now a compacted pit run but is not yet paved. WIP. No violations observed.
|
ESC14-00300
| General Inspection | 2/10/2015 | 2/11/2015 | 2/11/2015 9:51:23 AM | P | PASS |
|
|
Larry H. Miller collision center expansion project is now in operation under temp. occupancy. Parking lot still has some areas needing paving as well as landscaping. No trackout to Auto Drive, streets and gutters have been recently swept.
No corrections needed. Will continue to monitor stabilization of loose dirt. See also ESC14-00486 (carwash and south parking lot)
|
ESC14-01098
| Site Preparation | 2/10/2015 | 2/11/2015 | 2/11/2015 9:14:30 AM | A | PASS |
|
|
Justin Phone #: ###-####
Permit posted. Townhome ready for construction , two occupied homes on both sides of parcel will limit trackout.
Main BMP will be housekeeping. Regular sweeping, contain trash, etc.
|
ESC13-00443
| Aging Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 8:42:43 AM | | PASS |
|
|
|
ESC14-00328
| Site Preparation | 2/10/2015 | 2/11/2015 | 2/10/2015 4:22:47 PM | A | CANC |
|
|
data entry error
|