Inspections for the day of: Thursday, February 11, 2016.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE15-03729 Final2/10/20162/11/20162/11/2016 3:07:52 PMPPART
Room 102 Partial Final
Phone #: ###-#### Inspection requested via web by Kerri Hamilton room 102 ok to occupy
ELE16-00401 Temporary Service2/11/20162/11/20162/11/2016 2:07:39 PMPPASS
Temp Power Phone #: ###-#### Inspection requested via web by Zane Robertson t/s u/g n ok
ELE16-00400 Temporary Service2/11/20162/11/20162/11/2016 1:37:41 PMPPASS
Temp Power Phone #: ###-#### Inspection requested via web by Zane Robertson t/s u/g n ok
ELE16-00414 Electrical Rough-In2/11/20162/11/20162/11/2016 1:35:54 PMPFAIL
It should be open with people working, please call with any questions thanks Phone #: ###-#### Inspection requested via web by Brad Baker 300.4 nailplates needed@ type nm cable shall not be closer then 1 1/4" from face of faming member 334.30 type nm cabl shall be supported with 12" of a box 314 boxes shall be sized properly 590.6 all temporary recepts shall have GFCI protection remove wiring that is concealed in laundry room
ELE16-00329 Electrical Rough-In2/10/20162/11/20162/11/2016 12:22:52 PMPPASS
Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton 6th floor baths firred out wall and breakroom ok cover
ELE15-04025 Electrical Rough-In2/11/20162/11/20162/11/2016 11:44:05 AMAPASS
Ceiling Grid Inspection. Contact Rick Corn. Phone #: ###-#### Inspection requested via web by Cathy Duchek cieling ok cover
ELE16-00410 Electrical Rough-In2/10/20162/11/20162/11/2016 10:30:22 AMPPASS
Phone #: ###-#### Inspection requested via web by Jay Symonds kitchen and hall bath ok cover
ELE16-00409 Rough-In Permanent Service2/10/20162/11/20162/11/2016 10:23:14 AMACANC
Please call Casey. He is five minutes away from the job site and will meet the inspector on site.

Thanks Phone #: ###-#### Inspection requested via web by John Harvey needed to change for two different inspections
ELE16-00409 Electrical Rough-In2/11/20162/11/20162/11/2016 10:22:36 AMPPASS
Please call Casey. He is five minutes away from the job site and will meet the inspector on site.

Thanks Phone #: ###-#### Inspection requested via web by John Harvey garage addition rough-in ok cover
ELE16-00409 Permanent Service2/11/20162/11/20162/11/2016 10:21:49 AMPFAIL
Please call Casey. He is five minutes away from the job site and will meet the inspector on site.

Thanks Phone #: ###-#### Inspection requested via web by John Harvey 230.6 unfused service conductors shall have OCPD or encased in 2" of concrete when in installed in walls of a building
ELE16-00390 Electrical Rough-In2/10/20162/11/20162/11/2016 9:37:33 AMAPASS
Re inspect rough electrical on clubhouse Phone #: ###-#### Inspection requested via web by Bob Stephens clubhouse ok cover(electrical room not ready at this point will call for another inspection on later date)
ELE15-02908 Electrical Rough-In2/11/20162/11/20162/11/2016 9:37:29 AMAPASS
we are requesting a final for the warehouse only for this morning. Our contact is Rod @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate cieling in washbay electrical room ok cover
ELE16-00040 Electrical Rough-In2/11/20162/11/20162/11/2016 9:05:08 AMACANC
we are requesting a ceiling rough-in inspection for this morning. our contact is Rod @ ###-####. thank you. Phone #: ###-#### Inspection requested via web by Clint Tate needed final for warehouse
ELE16-00040 Final2/11/20162/11/20162/11/2016 9:04:43 AMPPASS
we are requesting a ceiling rough-in inspection for this morning. our contact is Rod @ ###-####. thank you. Phone #: ###-#### Inspection requested via web by Clint Tate final on warehouse ok