BLD96-02845
| INSP - Energy code compliance | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | | PASS |
|
|
/ / 316 -
|
BLD96-02845
| INSP - Framing/Rough-in | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | | PASS |
|
|
/ / 316 -
|
BLD96-02845
| INSP - Conference | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | | PASS |
|
|
/ / 316 - Met with builder, framer, and insulator....corrections worke
|
BLD96-03078
| INSP - Energy code compliance | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | | PASS |
|
|
/ / 316 -
|
BLD96-03178
| INSP - Footings | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | | PART |
|
|
/ / 316 - Poured W/O insp....Called contractor...setbacks, height, and OK.
|
BLD96-01379
| INSP - Framing/Rough-in | 2/11/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | A | CANC |
|
|
02/12/97 316 - Cancel ...Will do 2/13/97
|
BLD96-01906
| INSP - Carpentry | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | P | PART |
|
|
02/12/97 316 - BOND BEAM OK pending special inspection and approval...12
|
BLD96-03078
| INSP - Framing/Rough-in | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | P | PASS |
|
|
02/12/97 316 - FRAME REINSPECT OK
|
BLD96-02944
| INSP - Framing/Rough-in | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | P | FAIL |
|
|
02/12/97 316 - C/N...Misc ch 23...need approved plans.
|
BLD96-03179
| INSP - Footings | 2/11/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | P | PART |
|
|
02/12/97 316 - Poured W/O inspection.....Talked to contractor on phone.. and soil appear to be OK.
|
BLD96-03187
| INSP - Energy code compliance | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | P | PASS |
|
|
02/12/97 316 -
|
BLD96-03187
| INSP - Framing/Rough-in | 2/12/1997 | 2/12/1997 | 2/12/1997 12:00:00 AM | P | PASS |
|
|
02/12/97 316 - FRAME REINSPECT OK
|