Inspections for the day of: Tuesday, February 12, 2002.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-00234 BLD-Framing/Rough-in2/11/20022/12/20022/12/2002 12:00:00 AMAFAIL
Scheduled by Inspector: 340 On 2/11/2002 4:19:02 PM wendell 8668492,c/n: verify/justify glazed block at 2hr wall at ambulance bay at north ext; complete firestops, chk stair rails... 2/12/2002 6:17:26 PM
BLD00-02394 BLD-Conference2/11/20022/12/20022/12/2002 12:00:00 AMAPASS
Scheduled by Inspector: 340 On 2/11/2002 4:19:42 PM ...met w/ Mike Cotner...need further statement by eng'r for struct upgrade. keep c/n2/12/2002 12:50:40 PM 2/12/2002 12:50:54 PM
BLD01-00539 BLD-Framing/Rough-in2/11/20022/12/20022/12/2002 12:00:00 AMAPART
###-#### firestop floors, clarify shaft penetration(hvac) 2/12/2002 12:51:36 PM
BLD00-03361 BLD-Conference2/11/20022/12/20022/12/2002 12:00:00 AMAPASS
Scheduled by Inspector: 340 On 2/11/2002 2:33:20 PM ###-#### shell, need engs' affidavits; w/ BLD00-02375, add'l "shell" for concrete 2/12/2002 6:12:27 PM
BLD01-00602 BLD-Framing/Rough-in2/11/20022/12/20022/12/2002 12:00:00 AMPNR
Scheduled by a contractor via Hello! on 02/11/2002 at 15:15:52. Contact: ###-####.unable to contact 2/13/2002 3:38:13 PM
MEC01-01968 Pressure Test2/12/20022/12/20022/12/2002 12:00:00 AMPNH
Scheduled by a contractor via Hello! on 02/12/2002 at 10:08:10. Contact: ###-####.
BLD01-03277 BLD-Conference2/12/20022/12/20022/12/2002 12:00:00 AMPPART
###-#### RYAN call for frame insp 2/12/2002 6:04:35 PM
BLD00-02375 BLD-Conference2/12/20022/12/20022/12/2002 12:00:00 AMPPASS
Added by Inspector: 340 On 2/12/2002 6:15:33 PM c/n issued, need spec insp/eng's affidavits....chk cracks at "irregular" beams at bsmt lid (profile changed...sleeved areas show cracking at bottom edges)
BLD00-00081 BLD-Conference2/12/20022/12/20022/12/2002 12:00:00 AMPPASS
Added by Inspector: 340 On 2/12/2002 6:28:38 PM w/ Mike Cotner & supt re finals for west wing project...need eng's ok for MTI's observations & schmidt hammer tests
BLD01-01630 BLD-Conference2/12/20022/12/20022/12/2002 12:00:00 AMPPASS
Added by Inspector: 340 On 2/12/2002 6:29:39 PM work postponed til north end completed
BLD00-03449 BLD-Conference2/12/20022/12/20022/12/2002 12:00:00 AMPPASS
Added by Inspector: 340 On 2/12/2002 6:31:28 PM need affidavits, insp reports...all other agcy ok's for final