Inspections for the day of: Wednesday, February 12, 2014.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00023 INSP-Sprinkler Rough-in2/12/20142/12/20142/12/2014 5:17:26 PMPPART
Overhead fire sprinkler modifications passed rough-in inspection.
BLD12-01001 FIRE-Final Inspection2/11/20142/12/20142/12/2014 5:14:06 PMPFAIL
Project not in condition for final fire life safety approvals. Trade related work finals also pending.
FIR12-00639 INSP-Final Inspection2/11/20142/12/20142/12/2014 5:05:09 PMPFAIL
Missing trim and finishes at several locations, damaged SW head at the west stair 3rd floor, non-functional high/low air switch. Not ready for final.
FIR13-00315 INSP-Sprinkler Rough-in/Hydro2/11/20142/12/20142/12/2014 4:57:11 PMPNR
Hydro Phone #: ###-#### >> Inspection requested via web by John Venche *pending water supply
BLD14-00273 FIRE-Final Inspection2/12/20142/12/20142/12/2014 2:46:47 PMPPASS
Life safety okayed pending "door to remain....." signage and cover at one junction box. To be completed prior to structural final inspection.
FIR14-00033 INSP-Sprinkler Rough-in/Hydro2/11/20142/12/20142/12/2014 2:43:43 PMPPART
Provide quick response SW heads at four locations below overhead doors, noted two uprights at the SW corner not yet changed to QR. Final pending corrections, escutcheons and project finishes.
BLD13-02844 FIRE-Final Inspection2/7/20142/12/20142/12/2014 10:51:21 AMAPASS
Fire life safety inspection completed satisfactory.
FIR13-00315 INSP-Supply line flush2/11/20142/12/20142/12/2014 10:50:06 AMANR