Inspections for the day of: Friday, February 12, 2016.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE13-02103 ELE-Aging Inspection2/12/20162/12/20162/19/2016 2:35:41 PM CANC
ELE16-00424 Final2/11/20162/12/20162/12/2016 2:27:33 PMPPASS
Phone #: ###-#### Inspection requested via web by Randy Fletcher
Owner stated only circuit added is to receptacle in family room area for ironing. Final ok
ELE15-04015 Electrical Rough-In2/11/20162/12/20162/12/2016 1:57:45 PMPPASS
Job Foreman: Justin Hamby Phone #: ###-#### Inspection requested via web by Laurie Hoelscher Listing and disconnect confirmed. Rough in ok
ELE15-03807 Final2/12/20162/12/20162/12/2016 1:21:46 PMPFAIL
Phone #: ###-#### Inspection requested via web by Dan Rohl Post light has not been set yet and has wire hanging out of conuit.
ELE16-00114 Final2/12/20162/12/20162/12/2016 12:42:41 PMPFAIL
Phone #: ###-#### Inspection requested via web by Rowdy Monroe
210.8- Bath GFCI not working.
ELE16-00429 Permanent Service2/12/20162/12/20162/12/2016 11:46:58 AMPNH
key is on the meter base Phone #: ###-#### Inspection requested via web by John VanZandt No access key is not at or on meter base at time of inspection
ELE15-04077 Final2/11/20162/12/20162/12/2016 11:27:45 AMAPASS
led poles final Phone #: ###-#### Inspection requested via web by Tim Dunlop Final ok
ELE15-04022 Electrical Rough-In2/10/20162/12/20162/12/2016 10:55:35 AMAPASS
Jake is the contact Phone #: ###-#### Inspection requested via web by Shawna Gates Dental oral surgeon. Wall and hardlid rough in ok cover
ELE16-00425 Electrical Rough-In2/11/20162/12/20162/12/2016 9:21:16 AMAPASS
I should be there by 8:45 to let you in. Please call when headed my way. I will be waiting. ###-#### thanks Richard Phone #: ###-#### Inspection requested via web by Richard Corn
Phase 1 is master bathroom. At this time main bath and kitchen areas not to change much. These areas may just be updating lights and receptacles at current locations. Contractor to request inspections if extending or adding circuits in future. Master bath phase1 rough in ok cover
ELE15-04022 Electrical Rough-In2/10/20162/12/20162/10/2016 3:03:36 PMPCANC
Jake is the contact Phone #: ###-#### >> Inspection requested via web by Shawna Gates Inspection cancelled from web by: Shawna Gates