Inspections for the day of: Friday, February 12, 2016.
Number of inspections: 3
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00068 INSP-Sprinkler Rough-in2/12/20162/12/20162/12/2016 4:44:11 PMPPASS
Rough-in complete satisfactory. OK to cover. On-site plans annotated.
FIR15-00777 INSP-Final Inspection2/12/20162/12/20162/12/2016 2:04:33 PMPFAIL
Inspection was not a final. It was hydro test for the underground. System dropped to 172 psi from 200 psi, failed. System to be retested.
BLD15-02029 FIRE-Final Inspection2/12/20162/12/20162/12/2016 1:29:20 PMPPASS
Fire Life safety pass