Inspections for the day of: Wednesday, February 13, 2013.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-00032 FIRE-Final Inspection2/13/20132/13/20132/13/2013 3:46:15 PMPFAIL
Currently the mag lock doors are not working. They will need repaired and testes prior to final sign off. All other items appear ok.
BLD13-00137 FIRE-Conference2/13/20132/13/20132/13/2013 3:36:48 PMPDONE
Jeremy and I went over smoke alarm placement and general life safety requirements. I deferred his questions on the fire rated assembley to the building inspector.
FIR12-00651 INSP-Sprinkler Rough-in2/13/20132/13/20132/13/2013 3:29:08 PMPPASS
Sprinkler piping is ok to cover. Prior to a final sign off contractro needs to provide the original "job site copy" of the plans for review.
BLD12-03248 FIRE-Conference2/12/20132/13/20132/13/2013 3:24:22 PMADONE
Kevin and I went over duct detector placement on the new hvac unit and placement of the fire extinguishers. I also noted that the plans showed 10' racks but actually the racks are 12'. I asked him to discuss with plan review.
FIR12-00083 FIR-Aging Inspection2/13/20132/13/20132/13/2013 7:43:05 AM NR
Per steve with simplexgrinnell the DSC permits will be scheduled soon.